Lackenby (49.9 MW battery storage)

Lackenby is a 49.9 MW battery storage project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 24 October 2022; the record was last updated on 12 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
permission expiredstatus in REPD
12 August 2020record last updated
Redcar and Clevelandcouncil area

Planning timeline

DateStage
25 July 2019Application submitted
24 October 2019Planning permission granted
24 October 2022Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
permission expired
Record last updated
12 August 2020
Operator or applicant
EDF Energy Renewables
Planning authority
Redcar and Cleveland
Planning application reference
R/2019/0433/FF
Address (REPD)
Land at, Crow Lane, Old Lackenby, Middlesbrough
Council area (by location)
Redcar and Cleveland
Time to decision
13 weeks
REPD reference
7518

Earlier applications for this site

ApplicationMWSubmittedOutcome
Lackenby R/2017/0564/FF49.917 August 2017replaced by a revised application

Who decides

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Old Hall Farm, Lackenbybattery storage244application submitted0.3
Greystones Road, Grangetownbattery storage60approved, not built0.7
Wilton International, Greystones Road - Phase 1battery storage150approved, not built0.7
Tesside GigaParkbattery storage1,000application submitted2.1
Wiltonwind farm6.6application withdrawn3.1
Bank Field Wind Farmwind farm17application withdrawn3.6
Yearby Village - Tees Solar Farmsolar farm49.9approved, not built4.5
Tees Wind Northwind farm45abandoned4.6
Land at Woodhouse Farmsolar farm5operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5667, -1.1253).