Energy Projects Near You

Yearby Village - Tees Solar Farm (49.9 MW)

Yearby Village - Tees Solar Farm is a 49.9 MW solar farm project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 April 2024, not yet built; the record was last updated on 31 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
31 May 2024record last updated
Redcar and Clevelandcouncil area

Planning timeline

DateStage
3 January 2023Application submitted
30 April 2024Planning permission granted
30 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
31 May 2024
Operator or applicant
EDF Energy Renewables
Planning authority
Redcar and Cleveland
Planning application reference
R/2023/0002/FFM
Site area
75.0 ha
Address (REPD)
Near Yearby Village, South Of Redcar, Yearby, Redcar
Council area (by location)
Redcar and Cleveland
Time to decision
69 weeks
REPD reference
9353

Who decides

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wiltonwind farm6.6application withdrawn1.6
Tesside GigaParkbattery storage1,000application submitted3.1
Teesworks Battery Storage Projectbattery storage1,000application withdrawn3.6
Bank Field Wind Farmwind farm17application withdrawn4.2
Wilton International, Greystones Road - Phase 1battery storage150approved, not built4.4
Greystones Road, Grangetownbattery storage60approved, not built4.4
Lackenbybattery storage49.9permission expired4.5
Old Hall Farm, Lackenbybattery storage244application submitted4.7
Tees Wind Northwind farm45abandoned4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5881, -1.0666).