Tees Wind North (45 MW)
Tees Wind North is a 45 MW wind farm project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 29 June 2011.
45 MWwind farm
abandonedstatus in REPD
29 June 2011record last updated
Redcar and Clevelandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 December 2001 | Application submitted |
| 16 July 2002 | Planning permission granted |
| 16 July 2016 | Permission expired |
Project details
- Technology
- wind farm
- Capacity
- 45 MW
- Status (REPD)
- abandoned
- Record last updated
- 29 June 2011
- Operator or applicant
- Corus
- Planning authority
- Redcar and Cleveland
- Planning application reference
- R/2001/936/FF
- Turbines
- 18
- Address (REPD)
- Corus site , Middleborough , Teeside
- Council area (by location)
- Redcar and Cleveland
- Time to decision
- 30 weeks
- REPD reference
- 3125
Who decides
| Applications | Redcar and Cleveland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 1 (6%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Teesworks Battery Storage Project | battery storage | 1,000 | application withdrawn | 1.7 |
| Cowpen Bewley, Seal Sands Link Road | battery storage | 200 | application submitted | 2.2 |
| Tesside GigaPark | battery storage | 1,000 | application submitted | 3.0 |
| Wilton International, Greystones Road - Phase 1 | battery storage | 150 | approved, not built | 3.9 |
| Greystones Road, Grangetown | battery storage | 60 | approved, not built | 3.9 |
| Lackenby | battery storage | 49.9 | permission expired | 4.6 |
| Old Hall Farm, Lackenby | battery storage | 244 | application submitted | 4.9 |
| Yearby Village - Tees Solar Farm | solar farm | 49.9 | approved, not built | 4.9 |
| Wilton | wind farm | 6.6 | application withdrawn | 4.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6081, -1.1345).