Energy Projects Near You

Greystones Road, Grangetown (60 MW battery storage)

Greystones Road, Grangetown is a 60 MW battery storage project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 December 2021, not yet built; the record was last updated on 11 November 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWbattery storage
approved, not builtstatus in REPD
11 November 2021record last updated
Redcar and Clevelandcouncil area

Planning timeline

DateStage
29 October 2021Application submitted
17 December 2021Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
60 MW
Status (REPD)
approved, not built
Record last updated
11 November 2021
Operator or applicant
Sembcorp Utilities UK Limited
Planning authority
Redcar and Cleveland
Planning application reference
R/2021/0888/CL
Address (REPD)
Wilton Internationaln Off A1053 Greystones Roadn Grangetown
Council area (by location)
Redcar and Cleveland
Time to decision
7 weeks
Name in REPD
Greystones Road, Grangetown - Battery Energy Storage System
REPD reference
10081

Who decides

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wilton International, Greystones Road - Phase 1battery storage150approved, not built<0.1
Lackenbybattery storage49.9permission expired0.7
Old Hall Farm, Lackenbybattery storage244application submitted0.9
Tesside GigaParkbattery storage1,000application submitted1.6
Wiltonwind farm6.6application withdrawn3.2
Tees Wind Northwind farm45abandoned3.9
Bank Field Wind Farmwind farm17application withdrawn4.2
Teesworks Battery Storage Projectbattery storage1,000application withdrawn4.3
Yearby Village - Tees Solar Farmsolar farm49.9approved, not built4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5727, -1.1296).