Wilton (6.6 MW wind farm)
Wilton is a 6.6 MW wind farm project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 26 May 2016; the record was last updated on 27 May 2016.
6.6 MWwind farm
application withdrawnstatus in REPD
27 May 2016record last updated
Redcar and Clevelandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 19 February 2014 | Application submitted |
| 26 May 2016 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 6.6 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 27 May 2016
- Operator or applicant
- Airvolution Energy
- Planning authority
- Redcar and Cleveland
- Planning application reference
- R/2014/0074/FFM
- Turbines
- 2
- Address (REPD)
- Between Wilton and Yearby, Middlesbrough
- Council area (by location)
- Redcar and Cleveland
- REPD reference
- 4573
Who decides
| Applications | Redcar and Cleveland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 1 (6%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Yearby Village - Tees Solar Farm | solar farm | 49.9 | approved, not built | 1.6 |
| Tesside GigaPark | battery storage | 1,000 | application submitted | 2.3 |
| Bank Field Wind Farm | wind farm | 17 | application withdrawn | 2.9 |
| Lackenby | battery storage | 49.9 | permission expired | 3.1 |
| Wilton International, Greystones Road - Phase 1 | battery storage | 150 | approved, not built | 3.2 |
| Greystones Road, Grangetown | battery storage | 60 | approved, not built | 3.2 |
| Old Hall Farm, Lackenby | battery storage | 244 | application submitted | 3.3 |
| North Cote Farm & Park Farm, Dunsdale Solar Arrays | solar farm | 49.9 | approved, not built | 3.9 |
| A171, Guisborough Woods | battery storage | 28 | approved, not built | 3.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5766, -1.0807).