A171, Guisborough Woods (28 MW battery storage)

A171, Guisborough Woods is a 28 MW battery storage project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 April 2026, not yet built; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWbattery storage
approved, not builtstatus in REPD
19 May 2026record last updated
Redcar and Clevelandcouncil area

Planning timeline

DateStage
16 July 2025Application submitted
20 April 2026Planning permission granted
20 April 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
28 MW
Status (REPD)
approved, not built
Record last updated
19 May 2026
Operator or applicant
Harmony MS Limited
Planning authority
Redcar and Cleveland
Planning application reference
R/2025/0456/FFM
Address (REPD)
N/O A171, Guisborough
Council area (by location)
Redcar and Cleveland
Time to decision
40 weeks
Name in REPD
A171, Guisborough Woods - Battery Energy Storage System
REPD reference
17983

Who decides

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Cote Farm & Park Farm, Dunsdale Solar Arrayssolar farm49.9approved, not built<0.1
Land at Woodhouse Farmsolar farm5operational1.3
Bank Field Wind Farmwind farm17application withdrawn1.3
Wiltonwind farm6.6application withdrawn3.9
Old Hall Farm, Lackenbybattery storage244application submitted4.8
Lackenbybattery storage49.9permission expired4.9
Yearby Village - Tees Solar Farmsolar farm49.9approved, not built5.0
Greystones Road, Grangetownbattery storage60approved, not built5.5
Wilton International, Greystones Road - Phase 1battery storage150approved, not built5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.543, -1.062).