Energy Projects Near You

North Cote Farm & Park Farm, Dunsdale Solar Arrays (49.9 MW)

North Cote Farm & Park Farm, Dunsdale Solar Arrays is a 49.9 MW solar farm project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 December 2022, not yet built; the record was last updated on 27 February 2026. REPD records the planning permission as expiring on 23 December 2025, but the project holds a Contracts for Difference award (AR7a), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
27 February 2026record last updated
Redcar and Clevelandcouncil area

REPD records the planning permission as expiring on 23 December 2025, but the project holds a Contracts for Difference award (AR7a), so construction may have started.

Planning timeline

DateStage
19 August 2022Application submitted
23 December 2022Planning permission granted
23 December 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Elgin Energy
Planning authority
Redcar and Cleveland
Planning application reference
R/2022/0615/FFM
Site area
73.8 ha
Address (REPD)
N/O North Cote Farm And Park Farm, Dunsdale
Council area (by location)
Redcar and Cleveland
Time to decision
18 weeks
Contracts for Difference
AR7a
Name in REPD
North Cote Farm & Park Farm, Dunsdale - Solar Arrays
REPD reference
11983

Who decides

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
A171, Guisborough Woodsbattery storage28approved, not built<0.1
Land at Woodhouse Farmsolar farm5operational1.3
Bank Field Wind Farmwind farm17application withdrawn1.3
Wiltonwind farm6.6application withdrawn3.9
Old Hall Farm, Lackenbybattery storage244application submitted4.8
Lackenbybattery storage49.9permission expired4.9
Yearby Village - Tees Solar Farmsolar farm49.9approved, not built5.0
Greystones Road, Grangetownbattery storage60approved, not built5.5
Wilton International, Greystones Road - Phase 1battery storage150approved, not built5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.543, -1.062).