Energy Projects Near You

Solar, wind and battery projects near Saltburn-by-the-Sea (TS12)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS12 (Redcar and Cleveland): 1 is waiting for a planning decision, 7 approved but not yet running, 2 operational. The largest live scheme is Tesside GigaPark (1,000 MW battery storage, application submitted on 18 May 2026, no decision recorded), 9.8 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 12.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
1awaiting a decision
7approved, not running
2operational

Projects within 10 km of TS12

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kilton Wind Turbinewind turbinewind turbine2.5refusedupdated Dec 2014Jul 2014refused Nov 2014Dec 2014Redcar and Cleveland2.5
North Cote Farm & Park Farm, Dunsdale Solar Arrayssolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2026Aug 2022granted Dec 2022Feb 2026Redcar and Cleveland6.5
A171, Guisborough Woodsbattery storagebattery storage28approved, not builtupdated May 2026Jul 2025granted Apr 2026May 2026Redcar and Cleveland6.5
Yearby Village - Tees Solar Farmsolar farmsolar farm49.9approved, not builtupdated May 2024Jan 2023granted Apr 2024May 2024Redcar and Cleveland7.0
Bank Field Wind Farmwind farmwind farm17application withdrawnupdated Aug 2015Oct 2013—Aug 2015Redcar and Cleveland7.2
Wiltonwind farmwind farm6.6application withdrawnupdated May 2016Feb 2014—May 2016Redcar and Cleveland7.5
Land at Woodhouse Farmsolar farmsolar farm5operationalupdated Aug 2016May 2015granted Nov 2015Aug 2016Redcar and Cleveland7.7
Cleveland Potashbattery storagebattery storage6operationalupdated May 2019Jan 2016granted Mar 2016May 2019Redcar and Cleveland9.4
Tesside GigaParkbattery storagebattery storage1,000application submittedupdated Jun 2026May 2026—Jun 2026Redcar and Cleveland9.8
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sainsburys, Morgan Driverooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026Redcar and Cleveland6.9
Elring Klinger, Troisdorf Wayrooftop solarrooftop solar0.4approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Redcar and Cleveland8.4
Kirkleatham Street Solar Panel Arrayrooftop solarrooftop solar0.2under constructionupdated Jan 2022Jan 2022—Jan 2022Redcar and Cleveland9.0
Teesworks, Lackenbybattery storagebattery storage—approved, not builtupdated May 2025Dec 2024granted Mar 2025May 2025Redcar and Cleveland9.0

Distance from the average position of the TS12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3021099.8
Rooftop solar303000.8
Wind farm200000
Wind turbine100010
Battery storage412101,028

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 201512.3

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Redcar and Cleveland decides solar, wind and battery applications

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Redcar and Cleveland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TS12, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.