Solar, wind and battery projects near Saltburn-by-the-Sea (TS12)
13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS12 (Redcar and Cleveland): 1 is waiting for a planning decision, 7 approved but not yet running, 2 operational. The largest live scheme is Tesside GigaPark (1,000 MW battery storage, application submitted on 18 May 2026, no decision recorded), 9.8 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 12.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TS12
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Kilton Wind Turbinewind turbine | wind turbine | 2.5 | refusedupdated Dec 2014 | Jul 2014 | refused Nov 2014 | Dec 2014 | Redcar and Cleveland | 2.5 |
| North Cote Farm & Park Farm, Dunsdale Solar Arrayssolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2026 | Aug 2022 | granted Dec 2022 | Feb 2026 | Redcar and Cleveland | 6.5 |
| A171, Guisborough Woodsbattery storage | battery storage | 28 | approved, not builtupdated May 2026 | Jul 2025 | granted Apr 2026 | May 2026 | Redcar and Cleveland | 6.5 |
| Yearby Village - Tees Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated May 2024 | Jan 2023 | granted Apr 2024 | May 2024 | Redcar and Cleveland | 7.0 |
| Bank Field Wind Farmwind farm | wind farm | 17 | application withdrawnupdated Aug 2015 | Oct 2013 | — | Aug 2015 | Redcar and Cleveland | 7.2 |
| Wiltonwind farm | wind farm | 6.6 | application withdrawnupdated May 2016 | Feb 2014 | — | May 2016 | Redcar and Cleveland | 7.5 |
| Land at Woodhouse Farmsolar farm | solar farm | 5 | operationalupdated Aug 2016 | May 2015 | granted Nov 2015 | Aug 2016 | Redcar and Cleveland | 7.7 |
| Cleveland Potashbattery storage | battery storage | 6 | operationalupdated May 2019 | Jan 2016 | granted Mar 2016 | May 2019 | Redcar and Cleveland | 9.4 |
| Tesside GigaParkbattery storage | battery storage | 1,000 | application submittedupdated Jun 2026 | May 2026 | — | Jun 2026 | Redcar and Cleveland | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sainsburys, Morgan Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Jan 2026 | Apr 2026 | Redcar and Cleveland | 6.9 |
| Elring Klinger, Troisdorf Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Nov 2024 | Dec 2024 | Redcar and Cleveland | 8.4 |
| Kirkleatham Street Solar Panel Arrayrooftop solar | rooftop solar | 0.2 | under constructionupdated Jan 2022 | Jan 2022 | — | Jan 2022 | Redcar and Cleveland | 9.0 |
| Teesworks, Lackenbybattery storage | battery storage | — | approved, not builtupdated May 2025 | Dec 2024 | granted Mar 2025 | May 2025 | Redcar and Cleveland | 9.0 |
Distance from the average position of the TS12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 0 | 2 | 1 | 0 | 99.8 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 0.8 |
| Wind farm | 2 | 0 | 0 | 0 | 0 | 0 |
| Wind turbine | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 4 | 1 | 2 | 1 | 0 | 1,028 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Teesside Offshore Wind Farm | 62 | operationalupdated May 2015 | 12.3 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Redcar and Cleveland decides solar, wind and battery applications
| Applications | Redcar and Cleveland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 1 (6%) | 19% |
| Solar refused | 0 of 9 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in Redcar and Cleveland
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TS12, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.