Energy Projects Near You

Cleveland Potash (6 MW battery storage)

Cleveland Potash is a 6 MW battery storage project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 October 2017; the record was last updated on 16 May 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWbattery storage
operationalstatus in REPD
16 May 2019record last updated
Redcar and Clevelandcouncil area

Planning timeline

DateStage
7 January 2016Application submitted
2 March 2016Planning permission granted
1 June 2017Construction started
1 October 2017Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
6 MW
Status (REPD)
operational
Record last updated
16 May 2019
Operator or applicant
Kiwi Power
Planning authority
Redcar and Cleveland
Planning application reference
NYM/2015/0922/FL
Address (REPD)
Boulby Mine, Loftus, Saltburn-by-the-Sea, Cleveland
Council area (by location)
Redcar and Cleveland
Time to decision
8 weeks
REPD reference
6892

Who decides

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5561, -0.8216).