Land at Woodhouse Farm (5 MW solar farm)

Land at Woodhouse Farm is a 5 MW solar farm project in Redcar and Cleveland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2016; the record was last updated on 24 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
24 August 2016record last updated
Redcar and Clevelandcouncil area

Planning timeline

DateStage
21 May 2015Application submitted
24 November 2015Planning permission granted
20 January 2016Construction started
24 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
24 August 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Redcar and Cleveland
Planning application reference
R/2015/0328/FFM
Site area
10.1 ha
Address (REPD)
Land at Woodhouse Farm, Middlesbrough Road, Guisborough
Council area (by location)
Redcar and Cleveland
Time to decision
27 weeks
REPD reference
5309

Who decides

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
North Cote Farm & Park Farm, Dunsdale Solar Arrayssolar farm49.9approved, not built1.3
A171, Guisborough Woodsbattery storage28approved, not built1.3
Bank Field Wind Farmwind farm17application withdrawn1.7
Wiltonwind farm6.6application withdrawn4.6
Old Hall Farm, Lackenbybattery storage244application submitted4.7
Lackenbybattery storage49.9permission expired4.8
Wilton International, Greystones Road - Phase 1battery storage150approved, not built5.4
Greystones Road, Grangetownbattery storage60approved, not built5.4
Yearby Village - Tees Solar Farmsolar farm49.9approved, not built5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.535, -1.0758).