Energy Projects Near You

Solar, wind and battery projects near Redcar (TS10)

27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS10 (Redcar and Cleveland): 5 are waiting for a planning decision, 13 approved but not yet running, 1 operational. The largest live scheme is Tesside GigaPark (1,000 MW battery storage, application submitted on 18 May 2026, no decision recorded), 3.8 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 4.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27projects within 10 km
5awaiting a decision
13approved, not running
1operational

Projects within 10 km of TS10

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Yearby Village - Tees Solar Farmsolar farmsolar farm49.9approved, not builtupdated May 2024Jan 2023granted Apr 2024May 2024Redcar and Cleveland2.1
Teesworks Battery Storage Projectbattery storagebattery storage1,000application withdrawnupdated Nov 2025Dec 2024—Nov 2025Redcar and Cleveland2.5
Wiltonwind farmwind farm6.6application withdrawnupdated May 2016Feb 2014—May 2016Redcar and Cleveland3.4
Tesside GigaParkbattery storagebattery storage1,000application submittedupdated Jun 2026May 2026—Jun 2026Redcar and Cleveland3.8
Tees Wind Northwind farmwind farm45abandonedupdated Jun 2011Dec 2001granted Jul 2002Jun 2011Redcar and Cleveland4.2
PD Teesport Warehouse A, Bulk Teessolar farmsolar farm1approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025Redcar and Cleveland4.6
Wilton International, Greystones Road - Phase 1battery storagebattery storage150approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Redcar and Cleveland5.4
Greystones Road, Grangetownbattery storagebattery storage60approved, not builtupdated Nov 2021Oct 2021granted Dec 2021Nov 2021Redcar and Cleveland5.4
Lackenbybattery storagebattery storage49.9permission expiredupdated Aug 2020Jul 2019granted Oct 2019Aug 2020Redcar and Cleveland5.7
Old Hall Farm, Lackenbybattery storagebattery storage244application submittedupdated Sep 2025Aug 2025—Sep 2025Redcar and Cleveland6.0
Bank Field Wind Farmwind farmwind farm17application withdrawnupdated Aug 2015Oct 2013—Aug 2015Redcar and Cleveland6.2
Cowpen Bewley, Seal Sands Link Roadbattery storagebattery storage200application submittedupdated Feb 2025Jan 2025—Feb 2025Stockton-on-Tees6.4
North Cote Farm & Park Farm, Dunsdale Solar Arrayssolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2026Aug 2022granted Dec 2022Feb 2026Redcar and Cleveland7.1
A171, Guisborough Woodsbattery storagebattery storage28approved, not builtupdated May 2026Jul 2025granted Apr 2026May 2026Redcar and Cleveland7.1
Land at Woodhouse Farmsolar farmsolar farm5operationalupdated Aug 2016May 2015granted Nov 2015Aug 2016Redcar and Cleveland8.0
Graythorp Wind Turbinewind turbinewind turbine7.5application withdrawnupdated Aug 2018Jun 2014—Aug 2018Hartlepool9.4
Tofts Road - Single Wind Turbinewind turbinewind turbine4.3application submittedupdated Sep 2025Jul 2025—Sep 2025Hartlepool9.6
Tofts Road Wind Turbinewind turbinewind turbine7.5application withdrawnupdated Aug 2018Jun 2014—Aug 2018Hartlepool9.8
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kirkleatham Street Solar Panel Arrayrooftop solarrooftop solar0.2under constructionupdated Jan 2022Jan 2022—Jan 2022Redcar and Cleveland1.1
Teesworks, Lackenbybattery storagebattery storage—approved, not builtupdated May 2025Dec 2024granted Mar 2025May 2025Redcar and Cleveland1.1
Elring Klinger, Troisdorf Wayrooftop solarrooftop solar0.4approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Redcar and Cleveland2.1
CSG Limited, Holden Closerooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Redcar and Cleveland6.5
Teesside Recycling Centre, Puddlers Roadrooftop solarrooftop solar—approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Redcar and Cleveland7.3
Roman Terrace Solar Farmsolar farmsolar farm—approved, not builtupdated Nov 2025Jan 2025granted Jul 2025Nov 2025Redcar and Cleveland8.0
Huntsman Drive, Seal Sandsrooftop solarrooftop solar0.4application submittedMay 2026——Stockton-on-Tees8.4
Sainsburys, Morgan Driverooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026Redcar and Cleveland8.5
Cargo Fleet Lanerooftop solarrooftop solar0.2abandonedupdated Feb 2024Jun 2022—Feb 2024Middlesbrough9.5

Distance from the average position of the TS10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm50410101
Rooftop solar715001.4
Wind farm300000
Wind turbine310004.3
Battery storage934001,682

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 20154.6

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Redcar and Cleveland decides solar, wind and battery applications

ApplicationsRedcar and ClevelandUK
Decided applications (solar, wind, battery)1710,236
Refused1 (6%)19%
Solar refused0 of 912%
Onshore wind refused1 of 245%
Battery storage refused0 of 616%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Redcar and Cleveland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TS10, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.