Graythorp Wind Turbine (7.5 MW)

Graythorp Wind Turbine is a 7.5 MW wind turbine project in Hartlepool, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 30 August 2018; the record was last updated on 30 August 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind turbine
application withdrawnstatus in REPD
30 August 2018record last updated
Hartlepoolcouncil area

Planning timeline

DateStage
23 June 2014Application submitted
30 August 2018Application withdrawn

Project details

Technology
wind turbine
Capacity
7.5 MW
Status (REPD)
application withdrawn
Record last updated
30 August 2018
Operator or applicant
Seneca Global Energy
Planning authority
Hartlepool
Planning application reference
H/2014/0252
Appeal reference
APP/H0724/V/15/3136429
Turbines
1
Turbine height
207 m
Address (REPD)
Land at Graythorp Industrial Estate, Hartlepool
Council area (by location)
Hartlepool
REPD reference
4476

Who decides

ApplicationsHartlepoolUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused1 of 1212%
Onshore wind refused0 of 345%
Battery storage refused0 of 316%
Median time from submission to decision32.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tofts Road Wind Turbinewind turbine7.5application withdrawn0.6
Brenda Road Wind Turbinewind turbine7.5application withdrawn1.1
Cowpen Bewley, Seal Sands Link Roadbattery storage200application submitted4.1
Land at Bluehouse Farmsolar farm5operational4.2
Worset Lanebattery storage200approved, not built5.1
Tees Wind Northwind farm45abandoned5.7
Belasis Avenuebattery storage75approved, not built5.9
Teesworks Battery Storage Projectbattery storage1,000application withdrawn7.0
Worset Lane Solar Farmsolar farm50approved, not built7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.64, -1.2036).