Worset Lane Solar Farm (50 MW)

Worset Lane Solar Farm is a 50 MW solar farm project in Hartlepool, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 August 2021, not yet built; the record was last updated on 15 November 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
approved, not builtstatus in REPD
15 November 2023record last updated
Hartlepoolcouncil area

Planning timeline

DateStage
10 June 2020Application submitted
26 August 2021Planning permission granted
26 August 2026Permission expired

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
15 November 2023
Operator or applicant
Canadian Solar UK
Planning authority
Hartlepool
Planning application reference
H/2020/0175
Site area
62.9 ha
Address (REPD)
Worset Lane, Hartlepool
Council area (by location)
Hartlepool
Time to decision
63 weeks
Name in REPD
Worset Lane - Solar Farm
REPD reference
15247

Who decides

ApplicationsHartlepoolUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused1 of 1212%
Onshore wind refused0 of 345%
Battery storage refused0 of 316%
Median time from submission to decision32.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Home Farmsolar farm13abandoned1.5
High Volts Wind Farmwind farm5.5operational1.9
Whelley Hill Farm, Worset Lanebattery storage50approved, not built2.0
Whelley Hill Farmbattery storage25application withdrawn2.0
High Barnes Farm, Coal Lanebattery storage25approved, not built3.5
High Barnes Farm, Coal Lane Solar Farmsolar farm49.9approved, not built3.5
Worset Lanebattery storage200approved, not built3.9
Sheraton Wind Farm (Durham)wind farm10refused4.0
Sheraton Hall Solar Farmsolar farm49.9approved, not built4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.695, -1.2706).