Solar, wind and battery projects near Hartlepool (TS26)
35 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS26 (Hartlepool): 5 are waiting for a planning decision, 18 approved but not yet running, 4 operational. The largest live scheme is Worset Lane (200 MW battery storage, approved on 18 January 2023, not yet built; REPD status may be out of date), 1.4 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 10.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TS26
Projects of 1 MW and more (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Worset Lanebattery storage | battery storage | 200 | approved, not built may be out of dateupdated Jun 2022 | Jul 2022 | granted Jan 2023 | Jun 2022 | Hartlepool | 1.4 |
| Worset Lane Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Nov 2023 | Jun 2020 | granted Aug 2021 | Nov 2023 | Hartlepool | 2.5 |
| Home Farmsolar farm | solar farm | 13 | abandonedupdated Jan 2020 | Oct 2014 | granted Mar 2016 | Jan 2020 | Hartlepool | 4.0 |
| High Volts Wind Farmwind farm | wind farm | 5.5 | operationalupdated Dec 2009 | May 2001 | granted Mar 2002 | Dec 2009 | Hartlepool | 4.3 |
| Whelley Hill Farm, Worset Lanebattery storage | battery storage | 50 | approved, not builtupdated Jan 2024 | Feb 2023 | granted Dec 2023 | Jan 2024 | Hartlepool | 4.5 |
| Whelley Hill Farmbattery storage | battery storage | 25 | application withdrawnupdated May 2019 | Jan 2019 | — | May 2019 | Hartlepool | 4.5 |
| Brenda Road Wind Turbinewind turbine | wind turbine | 7.5 | application withdrawnupdated Aug 2018 | Jun 2014 | — | Aug 2018 | Hartlepool | 4.7 |
| Sheraton Wind Farm (Hartlepool)wind turbine | wind turbine | 2 | abandonedupdated Jul 2018 | Jan 2012 | — | Jul 2018 | Hartlepool | 4.8 |
| Tofts Road Wind Turbinewind turbine | wind turbine | 7.5 | application withdrawnupdated Aug 2018 | Jun 2014 | — | Aug 2018 | Hartlepool | 5.1 |
| Tofts Road - Single Wind Turbinewind turbine | wind turbine | 4.3 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Hartlepool | 5.2 |
| Benridge Farm, Fillpoke Lanesolar farm | solar farm | 48 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | County Durham | 5.6 |
| Benridge Farm, Fillpoke Lanebattery storage | battery storage | 12 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | County Durham | 5.6 |
| High Barnes Farm, Coal Lane Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated May 2026 | Aug 2024 | granted May 2025 | May 2026 | Hartlepool | 5.7 |
| High Barnes Farm, Coal Lanebattery storage | battery storage | 25 | approved, not builtupdated May 2026 | Aug 2024 | granted May 2025 | May 2026 | Hartlepool | 5.7 |
| Graythorp Wind Turbinewind turbine | wind turbine | 7.5 | application withdrawnupdated Aug 2018 | Jun 2014 | — | Aug 2018 | Hartlepool | 5.8 |
| Sheraton Wind Farm (Durham)wind farm | wind farm | 10 | refusedupdated Apr 2015 | Jan 2012 | refused Dec 2014 | Apr 2015 | County Durham | 6.4 |
| Sheraton Hall Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Sep 2025 | Dec 2020 | granted Dec 2023 | Sep 2025 | County Durham | 6.6 |
| Land at Bluehouse Farmsolar farm | solar farm | 5 | operationalupdated Dec 2016 | Sep 2015 | granted Nov 2015 | Dec 2016 | Hartlepool | 6.7 |
| Red Gap Moor Wind Farmwind farm | wind farm | 12.5 | operationalupdated Aug 2017 | May 2009 | granted Mar 2011 | Aug 2017 | Hartlepool | 7.3 |
| Stob House Farmsolar farm | solar farm | 4.9 | operationalupdated Dec 2016 | Sep 2015 | granted Jan 2016 | Dec 2016 | Hartlepool | 7.4 |
| Wynyard Business Park, North Chapell Lanerooftop solar | rooftop solar | 4 | approved, not built may be out of dateupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | Stockton-on-Tees | 8.4 |
| Cowpen Bewley, Seal Sands Link Roadbattery storage | battery storage | 200 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Stockton-on-Tees | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Lynnfield Primary School, Grosvenor Streetrooftop solar | rooftop solar | 0.2 | application submittedupdated Jan 2026 | Oct 2025 | — | Jan 2026 | Hartlepool | 0.9 |
| Clarence Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Hartlepool | 1.3 |
| The University Hospital Of Hartlepool, Holdforth Roadsolar farm | solar farm | 0.6 | approved, not builtupdated Apr 2025 | Jul 2024 | granted Apr 2025 | Apr 2025 | Hartlepool | 1.5 |
| The University Hospital Of Hartlepool, Holdforth Roadrooftop solar | rooftop solar | — | application withdrawnupdated May 2025 | Jul 2024 | — | May 2025 | Hartlepool | 1.5 |
| The University Hospital Of Hartlepool, Holdforth Roadrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Jan 2025 | granted Mar 2025 | Nov 2025 | Hartlepool | 1.5 |
| Stockton Streetrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Hartlepool | 1.6 |
| Omya UK Limited, Middleton Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Dec 2024 | Mar 2025 | Hartlepool | 2.3 |
| St Hilds C Of E School, King Oswy Driverooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | Hartlepool | 2.3 |
| J and B Recycling, Thomlinson Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Hartlepool | 2.4 |
| Nelson Farm, Nelson Farm Lanewind turbine | wind turbine | 0.2 | approved, not builtupdated Jan 2026 | Aug 2024 | granted Aug 2025 | Jan 2026 | Hartlepool | 3.6 |
| Sainsburys Supermarkets, Wynyard Retail Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2025 | Jul 2025 | granted Aug 2025 | Aug 2025 | Stockton-on-Tees | 8.4 |
| Northfield School And Sports College, Thames Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | Stockton-on-Tees | 9.4 |
| The Forum Theatre, Town Centrerooftop solar | rooftop solar | — | approved, not builtupdated Jun 2025 | Apr 2025 | granted Jun 2025 | Jun 2025 | Stockton-on-Tees | 9.8 |
Distance from the average position of the TS26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 1 | 4 | 2 | 0 | 198 |
| Rooftop solar | 12 | 1 | 10 | 0 | 0 | 8.2 |
| Wind farm | 3 | 0 | 0 | 2 | 1 | 0 |
| Wind turbine | 6 | 1 | 1 | 0 | 0 | 4.5 |
| Battery storage | 6 | 2 | 3 | 0 | 0 | 487 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Teesside Offshore Wind Farm | 62 | operationalupdated May 2015 | 10.1 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Hartlepool decides solar, wind and battery applications
| Applications | Hartlepool | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 1 (6%) | 19% |
| Solar refused | 1 of 12 | 12% |
| Onshore wind refused | 0 of 3 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 32.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TS26, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.