Energy Projects Near You

Solar, wind and battery projects near Billingham (TS23)

66 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS23 (Stockton-on-Tees): 4 are waiting for a planning decision, 42 approved but not yet running, 10 operational. The largest live scheme is Cowpen Bewley, Seal Sands Link Road (200 MW battery storage, application submitted on 22 January 2025, no decision recorded), 7.5 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 12.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

66projects within 10 km
4awaiting a decision
42approved, not running
10operational

Projects within 10 km of TS23

Projects of 1 MW and more (32)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Belasis Avenuebattery storagebattery storage75approved, not builtupdated Aug 2025Aug 2023granted Apr 2024Aug 2025Stockton-on-Tees1.8
Stob House Farmsolar farmsolar farm4.9operationalupdated Dec 2016Sep 2015granted Jan 2016Dec 2016Hartlepool2.7
Land at Bluehouse Farmsolar farmsolar farm5operationalupdated Dec 2016Sep 2015granted Nov 2015Dec 2016Hartlepool2.8
Norton Bottomssolar farmsolar farm5application withdrawnupdated Mar 2017Feb 2016—Mar 2017Stockton-on-Tees2.9
Wynyard Business Park, North Chapell Lanerooftop solarrooftop solar4approved, not built may be out of dateupdated Oct 2022Aug 2022granted Oct 2022Oct 2022Stockton-on-Tees3.1
The Brick Bankbattery storagebattery storage7permission expiredupdated Oct 2023Jul 2018granted Jan 2019Oct 2023Stockton-on-Tees4.4
Wilton Engineering Services, Port Clarence Offshore Baserooftop solarrooftop solar1.2approved, not builtupdated Jan 2026Sep 2025granted Sep 2025Jan 2026Stockton-on-Tees4.4
Red Gap Moor Wind Farmwind farmwind farm12.5operationalupdated Aug 2017May 2009granted Mar 2011Aug 2017Hartlepool4.7
Riverside Stadiumwind turbinewind turbine1.5permission expiredupdated Aug 2016May 2008granted Jul 2008Aug 2016Middlesbrough5.6
Letch Lane Solar Farmsolar farmsolar farm10.8approved, not built may be out of dateupdated Dec 2021Sep 2021granted Dec 2021Dec 2021Stockton-on-Tees6.0
Graythorp Wind Turbinewind turbinewind turbine7.5application withdrawnupdated Aug 2018Jun 2014—Aug 2018Hartlepool6.2
High Meadow Farmsolar farmsolar farm4operationalupdated Feb 2017Jul 2015granted Dec 2015Feb 2017Stockton-on-Tees6.3
Brenda Road Wind Turbinewind turbinewind turbine7.5application withdrawnupdated Aug 2018Jun 2014—Aug 2018Hartlepool6.5
Tofts Road Wind Turbinewind turbinewind turbine7.5application withdrawnupdated Aug 2018Jun 2014—Aug 2018Hartlepool6.5
Tofts Road - Single Wind Turbinewind turbinewind turbine4.3application submittedupdated Sep 2025Jul 2025—Sep 2025Hartlepool6.6
The Carrs - Meadow Farm Energy storage facilitybattery storagebattery storage57approved, not builtupdated Sep 2023Apr 2023granted Sep 2023Sep 2023Stockton-on-Tees6.7
California Farm Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2026Jun 2022granted Mar 2023Feb 2026Stockton-on-Tees6.7
Cowley Complex, Stockton on Teessolar farmsolar farm120under constructionupdated May 2024——May 2024Stockton-on-Tees6.9
Bowesfield Flexible Energy Parkbattery storagebattery storage8approved, not built may be out of dateupdated Oct 2021Jan 2021granted Oct 2021Oct 2021Stockton-on-Tees7.2
Cowpen Bewley, Seal Sands Link Roadbattery storagebattery storage200application submittedupdated Feb 2025Jan 2025—Feb 2025Stockton-on-Tees7.5
Lambs Hillwind farmwind farm8operationalupdated Feb 2017Oct 2010granted Dec 2011Feb 2017Stockton-on-Tees7.5
High Barnes Farm, Coal Lane Solar Farmsolar farmsolar farm49.9approved, not builtupdated May 2026Aug 2024granted May 2025May 2026Hartlepool8.4
High Barnes Farm, Coal Lanebattery storagebattery storage25approved, not builtupdated May 2026Aug 2024granted May 2025May 2026Hartlepool8.4
Eaglescliffe Solar Farmsolar farmsolar farm5operationalupdated May 2017Sep 2015granted Dec 2015May 2017Stockton-on-Tees8.9
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagesolar farmsolar farm50approved, not builtupdated Jul 2022Jun 2022granted Nov 2022Jul 2022Stockton-on-Tees9.2
PD Teesport Warehouse A, Bulk Teessolar farmsolar farm1approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025Redcar and Cleveland9.4
Butterwick Moorwind farmwind farm20.5operationalupdated Aug 2011Jan 2007granted Jun 2007Aug 2011County Durham9.4
Walkwaywind farmwind farm14operationalupdated May 2009Nov 2004granted Feb 2005May 2009County Durham9.4
High Volts Wind Farmwind farmwind farm5.5operationalupdated Dec 2009May 2001granted Mar 2002Dec 2009Hartlepool9.4
Worset Lane Solar Farmsolar farmsolar farm50approved, not builtupdated Nov 2023Jun 2020granted Aug 2021Nov 2023Hartlepool9.5
Worset Lanebattery storagebattery storage200approved, not built may be out of dateupdated Jun 2022Jul 2022granted Jan 2023Jun 2022Hartlepool9.6
Tees Wind Northwind farmwind farm45abandonedupdated Jun 2011Dec 2001granted Jul 2002Jun 2011Redcar and Cleveland9.7
Smaller schemes under 1 MW, mostly rooftop solar (34)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Forum Theatre, Town Centrerooftop solarrooftop solar—approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025Stockton-on-Tees0.4
Northfield School And Sports College, Thames Roadrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Stockton-on-Tees1.8
Sainsburys Supermarkets, Wynyard Retail Parkrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jul 2025granted Aug 2025Aug 2025Stockton-on-Tees3.1
Bulkhaul, Brignell Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2025Feb 2025granted Mar 2025May 2025Middlesbrough3.5
Riverside Park Industrial Estatebattery storagebattery storage0.2approved, not builtupdated Jun 2025Sep 2024granted May 2025Jun 2025Middlesbrough3.5
Riverside Park Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022Middlesbrough3.9
Armadillo Self Storage, North Tees Industrial Estaterooftop solarrooftop solar0.1approved, not builtupdated Jun 2025May 2025granted May 2025Jun 2025Stockton-on-Tees4.1
Zetland Multi Storey Car Park, Station Streetrooftop solarrooftop solar—approved, not builtupdated Nov 2022Aug 2022granted Sep 2022Nov 2022Middlesbrough4.6
David Lloyd Club, Tees Barrage Wayrooftop solarrooftop solar0.5approved, not builtupdated Nov 2023Jul 2023granted Nov 2023Nov 2023Stockton-on-Tees4.9
Albert Road Rooftop Solar Panelsrooftop solarrooftop solar0.2operationalupdated Sep 2021Nov 2020granted Mar 2021Sep 2021Middlesbrough5.2
Dunedin House,Columbia Driverooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Stockton-on-Tees5.4
Endeavour Houserooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Stockton-on-Tees5.4
Sainsburys Supermarket, Barlborough Avenuerooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Stockton-on-Tees5.4
Norton Substation, Letch Lanebattery storagebattery storage—approved, not builtupdated Jan 2024Oct 2023granted Jan 2024Jan 2024Stockton-on-Tees5.4
Hollywood Bowl, Aintree Oval Solar Photovoltaics Panelsrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025Middlesbrough5.5
Huntsman Drive, Seal Sandsrooftop solarrooftop solar0.4application submittedMay 2026——Stockton-on-Tees5.7
Breckon Hill Primary School, Breckon Hill Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Middlesbrough6.1
The North West & South East Sides Of The A19 Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Dec 2025Sep 2024granted Nov 2025Dec 2025Middlesbrough6.4
California Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2026Jun 2022granted Mar 2023Feb 2026Stockton-on-Tees6.7
Fairfield Primary School, Glenfield Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Stockton-on-Tees6.7
Cargo Fleet Lanerooftop solarrooftop solar0.2abandonedupdated Feb 2024Jun 2022—Feb 2024Middlesbrough6.9
The Vale - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Jun 2025Sep 2024refused May 2025Jun 2025Middlesbrough6.9
Roman Terrace Solar Farmsolar farmsolar farm—approved, not builtupdated Nov 2025Jan 2025granted Jul 2025Nov 2025Redcar and Cleveland7.2
Teesside Recycling Centre, Puddlers Roadrooftop solarrooftop solar—approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Redcar and Cleveland7.7
Motorpoint, Yarm Road Solar photovoltaics panelsrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Jul 2022May 2022Stockton-on-Tees8.0
J and B Recycling, Thomlinson Roadrooftop solarrooftop solar0.9approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Hartlepool8.6
Marton Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Dec 2025Aug 2025refused Oct 2025Dec 2025Middlesbrough8.8
CSG Limited, Holden Closerooftop solarrooftop solar0.2approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Redcar and Cleveland8.9
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Jul 2022Jun 2022granted Nov 2022Jul 2022Stockton-on-Tees9.2
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagesolar farmsolar farm—approved, not built may be out of dateupdated Jul 2022Jul 2022granted Nov 2022Jul 2022Stockton-on-Tees9.2
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Jul 2022Jul 2022granted Nov 2022Jul 2022Stockton-on-Tees9.2
Stockton Streetrooftop solarrooftop solar0.6approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Hartlepool9.2
Lynnfield Primary School, Grosvenor Streetrooftop solarrooftop solar0.2application submittedupdated Jan 2026Oct 2025—Jan 2026Hartlepool9.6
Clarence Roadrooftop solarrooftop solar0.6approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Hartlepool9.9

Distance from the average position of the TS23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm140940332
Rooftop solar262221011.9
Wind farm600500
Wind turbine510004.3
Battery storage1511102565

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 201512.8

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Stockton-on-Tees decides solar, wind and battery applications

ApplicationsStockton-on-TeesUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 2012%
Onshore wind refused0 of 345%
Battery storage refused0 of 916%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Stockton-on-Tees

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TS23, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.