Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storage (50 MW)
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storage is a 50 MW solar farm project in Stockton-on-Tees, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 November 2022, not yet built; the record was last updated on 20 July 2022.
50 MWsolar farm
approved, not builtstatus in REPD
20 July 2022record last updated
Stockton-on-Teescouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 June 2022 | Application submitted |
| 23 November 2022 | Planning permission granted |
Project details
- Technology
- solar farm
- Capacity
- 50 MW
- Status (REPD)
- approved, not built
- Record last updated
- 20 July 2022
- Operator or applicant
- Canadian Solar & Novergy
- Planning authority
- Stockton-on-Tees
- Planning application reference
- 22/1499/FUL
- Site area
- 127.4 ha
- Address (REPD)
- S/O Gately Moor Reservoir Near Redmarshall Stockton-On-Tees
- Council area (by location)
- Stockton-on-Tees
- Time to decision
- 21 weeks
- Contracts for Difference
- AR6
- Name in REPD
- Gately Moor Reservoir, Redmarshall - Solar Farm & Battery Storage
- REPD reference
- 11691
The scheme also includes battery storage, recorded separately in REPD (approved, not built).
Who decides
| Applications | Stockton-on-Tees | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 32 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 20 | 12% |
| Onshore wind refused | 0 of 3 | 45% |
| Battery storage refused | 0 of 9 | 16% |
| Median time from submission to decision | 16.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Newbiggin Wind Farm | wind farm | 6 | refused | 1.6 |
| The Carrs - Meadow Farm Energy storage facility | battery storage | 57 | approved, not built | 2.6 |
| California Farm Solar Farm & Battery Storage | solar farm | 49.9 | approved, not built | 2.6 |
| Letch Lane Solar Farm | solar farm | 10.8 | approved, not built | 3.2 |
| Long Pasture Farm, Little Stainton Solar Farm | solar farm | 49.9 | approved, not built | 3.6 |
| Cowley Complex, Stockton on Tees | solar farm | 120 | under construction | 4.3 |
| Byers Gill Solar Farm | solar farm | 180 | approved, not built | 4.4 |
| A1 Wind Farm | wind farm | 20 | application withdrawn | 5.2 |
| Moor House Wind Farm | wind farm | 12 | operational | 5.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.576, -1.416).