Energy Projects Near You

Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storage (50 MW)

Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storage is a 50 MW solar farm project in Stockton-on-Tees, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 November 2022, not yet built; the record was last updated on 20 July 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
approved, not builtstatus in REPD
20 July 2022record last updated
Stockton-on-Teescouncil area

Planning timeline

DateStage
29 June 2022Application submitted
23 November 2022Planning permission granted

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
20 July 2022
Operator or applicant
Canadian Solar & Novergy
Planning authority
Stockton-on-Tees
Planning application reference
22/1499/FUL
Site area
127.4 ha
Address (REPD)
S/O Gately Moor Reservoir Near Redmarshall Stockton-On-Tees
Council area (by location)
Stockton-on-Tees
Time to decision
21 weeks
Contracts for Difference
AR6
Name in REPD
Gately Moor Reservoir, Redmarshall - Solar Farm & Battery Storage
REPD reference
11691

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsStockton-on-TeesUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 2012%
Onshore wind refused0 of 345%
Battery storage refused0 of 916%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newbiggin Wind Farmwind farm6refused1.6
The Carrs - Meadow Farm Energy storage facilitybattery storage57approved, not built2.6
California Farm Solar Farm & Battery Storagesolar farm49.9approved, not built2.6
Letch Lane Solar Farmsolar farm10.8approved, not built3.2
Long Pasture Farm, Little Stainton Solar Farmsolar farm49.9approved, not built3.6
Cowley Complex, Stockton on Teessolar farm120under construction4.3
Byers Gill Solar Farmsolar farm180approved, not built4.4
A1 Wind Farmwind farm20application withdrawn5.2
Moor House Wind Farmwind farm12operational5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.576, -1.416).