Energy Projects Near You

The Carrs - Meadow Farm Energy storage facility (57 MW)

The Carrs - Meadow Farm Energy storage facility is a 57 MW battery storage project in Stockton-on-Tees, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 September 2023, not yet built; the record was last updated on 26 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

57 MWbattery storage
approved, not builtstatus in REPD
26 September 2023record last updated
Stockton-on-Teescouncil area

Planning timeline

DateStage
26 April 2023Application submitted
21 September 2023Planning permission granted
21 September 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
57 MW
Status (REPD)
approved, not built
Record last updated
26 September 2023
Operator or applicant
BayWa r.e.
Planning authority
Stockton-on-Tees
Planning application reference
23/0752/FUL
Address (REPD)
Se/O The Carrs, Fishing Lakes, Letch Lane, Carlton, Stockton on Tees
Council area (by location)
Stockton-on-Tees
Time to decision
21 weeks
REPD reference
9207

Who decides

ApplicationsStockton-on-TeesUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 2012%
Onshore wind refused0 of 345%
Battery storage refused0 of 916%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
California Farm Solar Farm & Battery Storagesolar farm49.9approved, not built<0.1
Letch Lane Solar Farmsolar farm10.8approved, not built0.7
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagesolar farm50approved, not built2.6
Cowley Complex, Stockton on Teessolar farm120under construction2.8
Newbiggin Wind Farmwind farm6refused4.2
Eaglescliffe Solar Farmsolar farm5operational5.5
Foxton Lanewind farm6refused5.8
Lambs Hillwind farm8operational5.9
The Brick Bankbattery storage7permission expired6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5879, -1.3818).