Foxton Lane (6 MW wind farm)

Foxton Lane is a 6 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 10 October 2012; the record was last updated on 10 October 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
refusedstatus in REPD
10 October 2012record last updated
County Durhamcouncil area

Planning timeline

DateStage
14 July 2010Application submitted
10 October 2012Refused by the planning authority

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
refused
Record last updated
10 October 2012
Operator or applicant
Wind Prospect
Planning authority
County Durham
Planning application reference
7/2010/0236/DM
Turbines
3
Address (REPD)
Sedgefield, Co Durham
Council area (by location)
County Durham
Time to decision
117 weeks
REPD reference
3780

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cowley Complex, Stockton on Teessolar farm120under construction3.7
The Isles Wind Farmwind farm48application withdrawn4.2
A1 Wind Farmwind farm20application withdrawn5.0
Walkwaywind farm14operational5.2
Butterwick Moorwind farm20.5operational5.2
Byers Gill Solar Farmsolar farm180approved, not built5.6
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagesolar farm50approved, not built5.8
California Farm Solar Farm & Battery Storagesolar farm49.9approved, not built5.8
The Carrs - Meadow Farm Energy storage facilitybattery storage57approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6251, -1.4438).