The Isles Wind Farm (48 MW)

The Isles Wind Farm is a 48 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 21 January 2016; the record was last updated on 26 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
application withdrawnstatus in REPD
26 January 2016record last updated
County Durhamcouncil area

Planning timeline

DateStage
15 May 2014Application submitted
21 January 2016Application withdrawn

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
application withdrawn
Record last updated
26 January 2016
Operator or applicant
E.ON Climate and Renewables
Planning authority
County Durham
Planning application reference
DM/14/01210/FPA
Turbines
24
Address (REPD)
Land 1.5km east of Newton Aycliffe, County Durham
Council area (by location)
County Durham
REPD reference
4221

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Whinfield Solar Farmsolar farm33approved, not built3.5
A1 Wind Farmwind farm20application withdrawn3.8
Foxton Lanewind farm6refused4.2
Byers Gill Solar Farmsolar farm180approved, not built4.9
Moor House Wind Farmwind farm12operational5.4
Field at School Aycliffe Lanesolar farm5operational5.8
Long Pasture Farm, Little Stainton Solar Farmsolar farm49.9approved, not built6.3
Cowley Complex, Stockton on Teessolar farm120under construction7.7
Newbiggin Wind Farmwind farm6refused7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6226, -1.5097).