Moor House Wind Farm (12 MW)

Moor House Wind Farm is a 12 MW wind farm project in Darlington, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2017; the record was last updated on 1 May 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
1 May 2018record last updated
Darlingtoncouncil area

Planning timeline

DateStage
14 March 2011Application submitted
19 October 2011Planning permission granted
16 January 2017Construction started
15 December 2017Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
1 May 2018
Operator or applicant
Banks Renewables
Planning authority
Darlington
Planning application reference
11/00160/FUL
Turbines
6
Address (REPD)
Bishopton Lane, Great Burdon, Darlington
Council area (by location)
Darlington
Time to decision
31 weeks
Contracts for Difference
AR1
REPD reference
4642

Earlier applications for this site

ApplicationMWSubmittedOutcome
Moor House Wind Farm 09/00741/FUL2510 October 2009refused 12 November 2010

Who decides

ApplicationsDarlingtonUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1712%
Onshore wind refused1 of 345%
Battery storage refused0 of 116%
Median time from submission to decision12.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Byers Gill Solar Farmsolar farm180approved, not built1.1
Long Pasture Farm, Little Stainton Solar Farmsolar farm49.9approved, not built1.7
A1 Wind Farmwind farm20application withdrawn1.7
Whinfield Solar Farmsolar farm33approved, not built2.9
Newbiggin Wind Farmwind farm6refused4.0
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagesolar farm50approved, not built5.2
The Isles Wind Farmwind farm48application withdrawn5.4
Burtree Lane Solar farmsolar farm49.9under construction6.1
Foxton Lanewind farm6refused6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5746, -1.4972).