Energy Projects Near You

Renewable energy projects in Darlington

28 solar, wind or battery projects of 150 kW or more are located in Darlington (REPD, July 2026 extract): 0 pending, 18 approved but not running, 5 operational and 1 refused. The council refused 1 of 21 decided applications (5%; UK 19%), with a median 12 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28projects in the council area
0awaiting a decision
18approved, not running
5%of decisions refused

How Darlington decides

ApplicationsDarlingtonUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1712%
Onshore wind refused1 of 345%
Battery storage refused0 of 116%
Median time from submission to decision12.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Darlington

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Byers Gill Solar Farmsolar farmsolar farm180approved, not builtupdated Jul 2025Feb 2024granted Jul 2025Jul 2025
Burtree Lane Solar farmsolar farmsolar farm49.9under constructionupdated Mar 2026Mar 2022granted Jan 2023Mar 2026
Long Pasture Farm, Little Stainton Solar Farmsolar farmsolar farm49.9approved, not builtupdated Aug 2023Dec 2022granted Aug 2023Aug 2023
Long Pasture Farm, Little Stainton Solar Farmbattery storagebattery storage40approved, not builtupdated Aug 2023Dec 2022granted Aug 2023Aug 2023
Whinfield Solar Farmsolar farmsolar farm33approved, not built may be out of dateupdated Jan 2025Aug 2021granted Oct 2022Jan 2025
A1 Wind Farmwind farmwind farm20application withdrawnupdated Aug 2011Feb 2005—Aug 2011
Moor House Wind Farmwind farmwind farm12operationalupdated May 2018Mar 2011granted Oct 2011May 2018
Broken Scar Water Treatment Works Solar Farmsolar farmsolar farm9approved, not builtupdated Jan 2024Jan 2022granted Jun 2022Jan 2024
Newbiggin Wind Farmwind farmwind farm6refusedupdated Nov 2012Feb 2011refused Oct 2012Nov 2012
Field at School Aycliffe Lanesolar farmsolar farm5operationalupdated Dec 2015Jan 2015granted Jun 2015Dec 2015
Land West Of Hunger Hill Farmsolar farmsolar farm5operationalupdated Dec 2017May 2015granted Aug 2015Dec 2017
Rise Carr, Darlington / CLNR EES3-1battery storagebattery storage2.5operationalupdated Oct 2018——Oct 2018
Aldi Distribution Centre - Darlingtonrooftop solarrooftop solar1.2operationalupdated Dec 2015Jul 2013granted Sep 2013Dec 2015
Smaller schemes under 1 MW, mostly rooftop solar (15)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Morrisonsrooftop solarrooftop solar0.7approved, not builtupdated Feb 2022Feb 2022granted Apr 2022Feb 2022
Park Lane Solar panelsrooftop solarrooftop solar0.4approved, not built may be out of dateupdated Feb 2022May 2021granted Jan 2022Feb 2022
Queen Elizabeth Sixth Form College, Vane Terrace -Solar Panelsrooftop solarrooftop solar0.4approved, not builtupdated Sep 2025Jun 2025granted Sep 2025Sep 2025
Wyvern Academy, Eggleston Viewrooftop solarrooftop solar0.4approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025
Hurworth School, Croft Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Nov 2023granted Dec 2023Dec 2023
Longfield Academy Of Sportrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023
Heathfield Primary School, The Broadwayrooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025
The Rydal Academy, Rydal Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024
Darlington Memorial Hospital, Hollyhurst Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2026Dec 2025granted Jan 2026Feb 2026
Carlburybattery storagebattery storage0.2application withdrawnupdated Mar 2026Dec 2025—Mar 2026
The Dolphin Centrerooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025
Middlesbrough Football Club, Rockliffe Park -Solar Panelsrooftop solarrooftop solar0.1approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025
Harrowgate Hill, Darlington / CLNR ESS3-2battery storagebattery storage0.1decommissionedupdated Oct 2016——Oct 2016
High Northgate, Darlington / CLNR ESS3-3battery storagebattery storage0.1decommissionedupdated Oct 2016——Oct 2016
Byers Gill Solar Farmbattery storagebattery storage—approved, not builtupdated Jul 2025Feb 2024granted Jul 2025Jul 2025

Postcode districts in Darlington

DistrictProjects within 10 kmPendingApprovedOperational
DL1350245
DL2311205
DL3310205

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Darlington by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.