Whinfield Solar Farm (33 MW)

Whinfield Solar Farm is a 33 MW solar farm project in Darlington, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 October 2022, not yet built; the record was last updated on 16 January 2025. REPD records the planning permission as expiring on 4 October 2025, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

33 MWsolar farm
approved, not builtmay be out of datestatus in REPD
16 January 2025record last updated
Darlingtoncouncil area

REPD records the planning permission as expiring on 4 October 2025, but the project holds a Contracts for Difference award (AR6), so construction may have started.

Planning timeline

DateStage
9 August 2021Application submitted
4 October 2022Planning permission granted
4 October 2025Permission expired

Project details

Technology
solar farm
Capacity
33 MW
Status (REPD)
approved, not built
Record last updated
16 January 2025
Operator or applicant
Alpha Real Capital LLP
Planning authority
Darlington
Planning application reference
DM/21/02816/FPA
Site area
42.3 ha
Address (REPD)
Aycliffe Village & Adj Whinfield House, Lime Lane, Brafferton, Darlington
Council area (by location)
Darlington
Time to decision
60 weeks
Contracts for Difference
AR6
REPD reference
12339

Who decides

ApplicationsDarlingtonUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1712%
Onshore wind refused1 of 345%
Battery storage refused0 of 116%
Median time from submission to decision12.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
A1 Wind Farmwind farm20application withdrawn2.3
Moor House Wind Farmwind farm12operational2.9
Byers Gill Solar Farmsolar farm180approved, not built3.1
The Isles Wind Farmwind farm48application withdrawn3.5
Long Pasture Farm, Little Stainton Solar Farmsolar farm49.9approved, not built4.4
Field at School Aycliffe Lanesolar farm5operational4.7
Burtree Lane Solar farmsolar farm49.9under construction6.3
Foxton Lanewind farm6refused6.5
Newbiggin Wind Farmwind farm6refused6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5931, -1.5281).