Energy Projects Near You

Land West Of Hunger Hill Farm (5 MW solar farm)

Land West Of Hunger Hill Farm is a 5 MW solar farm project in Darlington, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2017; the record was last updated on 4 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 December 2017record last updated
Darlingtoncouncil area

Planning timeline

DateStage
19 May 2015Application submitted
13 August 2015Planning permission granted
12 December 2016Construction started
15 February 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 December 2017
Operator or applicant
Greencoat Capital
Planning authority
Darlington
Planning application reference
15/00484/FUL
Site area
19.0 ha
Address (REPD)
Land West Of Hunger Hill Farm,, Middleton St George, Brass Castle, Darlington
Council area (by location)
Darlington
Time to decision
12 weeks
REPD reference
5301

Who decides

ApplicationsDarlingtonUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1712%
Onshore wind refused1 of 345%
Battery storage refused0 of 116%
Median time from submission to decision12.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burtree Lane Solar farmsolar farm49.9under construction7.0
Long Pasture Farm, Little Stainton Solar Farmsolar farm49.9approved, not built7.1
Newbiggin Wind Farmwind farm6refused7.4
Moor House Wind Farmwind farm12operational7.6
Broken Scar Water Treatment Works Solar Farmsolar farm9approved, not built8.0
East Cowton Solar Farmsolar farm30.8application submitted8.1
Byers Gill Solar Farmsolar farm180approved, not built8.2
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagesolar farm50approved, not built8.9
Eaglescliffe Solar Farmsolar farm5operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5069, -1.4851).