Energy Projects Near You

Solar, wind and battery projects near Yarm (TS15)

21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS15 (Stockton-on-Tees): 1 is waiting for a planning decision, 11 approved but not yet running, 5 operational. The largest live scheme is Mowbray Battery Energy Storage Station (1,000 MW battery storage, application submitted on 19 December 2024, no decision recorded), 5.7 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 23.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21projects within 10 km
1awaiting a decision
11approved, not running
5operational

Projects within 10 km of TS15

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Seamer Wind Farm - Hambletonwind farmwind farm4operationalupdated Nov 2012Mar 2009granted Sep 2009Nov 2012Stockton-on-Tees4.8
Seamer Windfarm - Stockton on Teeswind farmwind farm6operationalupdated Nov 2012Mar 2009granted Aug 2009Nov 2012North Yorkshire5.0
Mowbray Battery Energy Storage Stationbattery storagebattery storage1,000application submittedupdated Feb 2025Dec 2024—Feb 2025North Yorkshire5.7
Eaglescliffe Solar Farmsolar farmsolar farm5operationalupdated May 2017Sep 2015granted Dec 2015May 2017Stockton-on-Tees6.1
Lambs Hillwind farmwind farm8operationalupdated Feb 2017Oct 2010granted Dec 2011Feb 2017Stockton-on-Tees6.6
Bowesfield Flexible Energy Parkbattery storagebattery storage8approved, not built may be out of dateupdated Oct 2021Jan 2021granted Oct 2021Oct 2021Stockton-on-Tees6.8
The Brick Bankbattery storagebattery storage7permission expiredupdated Oct 2023Jul 2018granted Jan 2019Oct 2023Stockton-on-Tees9.6
Land West Of Hunger Hill Farmsolar farmsolar farm5operationalupdated Dec 2017May 2015granted Aug 2015Dec 2017Darlington9.9
Smaller schemes under 1 MW, mostly rooftop solar (13)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Motorpoint, Yarm Road Solar photovoltaics panelsrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Jul 2022May 2022Stockton-on-Tees6.3
Stainton Way - Micro Energy storagebattery storagebattery storage0.2application withdrawnupdated May 2025Sep 2024—May 2025Middlesbrough7.0
Viewley Hill Academy, Andover Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Sep 2023granted Nov 2023Jan 2024Middlesbrough7.5
The North West & South East Sides Of The A19 Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Dec 2025Sep 2024granted Nov 2025Dec 2025Middlesbrough8.4
Dunedin House,Columbia Driverooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Stockton-on-Tees8.6
Endeavour Houserooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Stockton-on-Tees8.6
Rainbow Leisure Centre, Dalby Wayrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025Middlesbrough8.7
Hollywood Bowl, Aintree Oval Solar Photovoltaics Panelsrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025Middlesbrough9.0
Fairfield Primary School, Glenfield Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Stockton-on-Tees9.0
David Lloyd Club, Tees Barrage Wayrooftop solarrooftop solar0.5approved, not builtupdated Nov 2023Jul 2023granted Nov 2023Nov 2023Stockton-on-Tees9.2
Sainsburys Supermarket, Barlborough Avenuerooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Stockton-on-Tees9.4
The Vale - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Jun 2025Sep 2024refused May 2025Jun 2025Middlesbrough9.7
Marton Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Dec 2025Aug 2025refused Oct 2025Dec 2025Middlesbrough10.0

Distance from the average position of the TS15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200200
Rooftop solar909002.3
Wind farm300300
Battery storage712021,008

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 201523.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Stockton-on-Tees decides solar, wind and battery applications

ApplicationsStockton-on-TeesUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 2012%
Onshore wind refused0 of 345%
Battery storage refused0 of 916%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Stockton-on-Tees

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TS15, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.