Seamer Windfarm - Stockton on Tees (6 MW)

Seamer Windfarm - Stockton on Tees is a 6 MW wind farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2012; the record was last updated on 29 November 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
operationalstatus in REPD
29 November 2012record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
27 March 2009Application submitted
25 August 2009Planning permission granted
1 April 2012Construction started
1 November 2012Operational

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
operational
Record last updated
29 November 2012
Operator or applicant
Broadview Energy
Planning authority
Stockton-on-Tees
Planning application reference
09/0736/EIS
Turbines
3
Address (REPD)
Between the villages of Hilton and Seamer on the Stockton-on-Tees and North Yorkshire boundaries.
Council area (by location)
North Yorkshire
Time to decision
22 weeks
REPD reference
3984

Who decides

ApplicationsStockton-on-TeesUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 2012%
Onshore wind refused0 of 345%
Battery storage refused0 of 916%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bowesfield Flexible Energy Parkbattery storage8approved, not built6.7
Lambs Hillwind farm8operational7.3
Eaglescliffe Solar Farmsolar farm5operational8.1
Mowbray Battery Energy Storage Stationbattery storage1,000application submitted8.5
The Brick Bankbattery storage7permission expired8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4942, -1.2585).