Energy Projects Near You

Solar, wind and battery projects near Stockton-on-Tees (TS19)

55 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TS19 (Stockton-on-Tees): 1 is waiting for a planning decision, 36 approved but not yet running, 8 operational. The largest live scheme is Byers Gill Solar Farm (180 MW solar farm, approved on 23 July 2025, not yet built), 9.1 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 17.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

55projects within 10 km
1awaiting a decision
36approved, not running
8operational

Projects within 10 km of TS19

Projects of 1 MW and more (25)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Letch Lane Solar Farmsolar farmsolar farm10.8approved, not built may be out of dateupdated Dec 2021Sep 2021granted Dec 2021Dec 2021Stockton-on-Tees2.3
High Meadow Farmsolar farmsolar farm4operationalupdated Feb 2017Jul 2015granted Dec 2015Feb 2017Stockton-on-Tees2.7
The Carrs - Meadow Farm Energy storage facilitybattery storagebattery storage57approved, not builtupdated Sep 2023Apr 2023granted Sep 2023Sep 2023Stockton-on-Tees2.7
California Farm Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2026Jun 2022granted Mar 2023Feb 2026Stockton-on-Tees2.7
The Brick Bankbattery storagebattery storage7permission expiredupdated Oct 2023Jul 2018granted Jan 2019Oct 2023Stockton-on-Tees3.3
Lambs Hillwind farmwind farm8operationalupdated Feb 2017Oct 2010granted Dec 2011Feb 2017Stockton-on-Tees3.6
Norton Bottomssolar farmsolar farm5application withdrawnupdated Mar 2017Feb 2016—Mar 2017Stockton-on-Tees3.7
Bowesfield Flexible Energy Parkbattery storagebattery storage8approved, not built may be out of dateupdated Oct 2021Jan 2021granted Oct 2021Oct 2021Stockton-on-Tees4.0
Eaglescliffe Solar Farmsolar farmsolar farm5operationalupdated May 2017Sep 2015granted Dec 2015May 2017Stockton-on-Tees4.1
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagesolar farmsolar farm50approved, not builtupdated Jul 2022Jun 2022granted Nov 2022Jul 2022Stockton-on-Tees4.7
Cowley Complex, Stockton on Teessolar farmsolar farm120under constructionupdated May 2024——May 2024Stockton-on-Tees5.0
Belasis Avenuebattery storagebattery storage75approved, not builtupdated Aug 2025Aug 2023granted Apr 2024Aug 2025Stockton-on-Tees5.7
Newbiggin Wind Farmwind farmwind farm6refusedupdated Nov 2012Feb 2011refused Oct 2012Nov 2012Darlington6.1
Wynyard Business Park, North Chapell Lanerooftop solarrooftop solar4approved, not built may be out of dateupdated Oct 2022Aug 2022granted Oct 2022Oct 2022Stockton-on-Tees6.2
Stob House Farmsolar farmsolar farm4.9operationalupdated Dec 2016Sep 2015granted Jan 2016Dec 2016Hartlepool6.9
Wilton Engineering Services, Port Clarence Offshore Baserooftop solarrooftop solar1.2approved, not builtupdated Jan 2026Sep 2025granted Sep 2025Jan 2026Stockton-on-Tees7.5
Land at Bluehouse Farmsolar farmsolar farm5operationalupdated Dec 2016Sep 2015granted Nov 2015Dec 2016Hartlepool7.8
Red Gap Moor Wind Farmwind farmwind farm12.5operationalupdated Aug 2017May 2009granted Mar 2011Aug 2017Hartlepool7.9
Riverside Stadiumwind turbinewind turbine1.5permission expiredupdated Aug 2016May 2008granted Jul 2008Aug 2016Middlesbrough8.1
Long Pasture Farm, Little Stainton Solar Farmsolar farmsolar farm49.9approved, not builtupdated Aug 2023Dec 2022granted Aug 2023Aug 2023Darlington8.3
Long Pasture Farm, Little Stainton Solar Farmbattery storagebattery storage40approved, not builtupdated Aug 2023Dec 2022granted Aug 2023Aug 2023Darlington8.3
Foxton Lanewind farmwind farm6refusedupdated Oct 2012Jul 2010refused Oct 2012Oct 2012County Durham8.4
Byers Gill Solar Farmsolar farmsolar farm180approved, not builtupdated Jul 2025Feb 2024granted Jul 2025Jul 2025Darlington9.1
A1 Wind Farmwind farmwind farm20application withdrawnupdated Aug 2011Feb 2005—Aug 2011Darlington9.8
Moor House Wind Farmwind farmwind farm12operationalupdated May 2018Mar 2011granted Oct 2011May 2018Darlington9.9
Smaller schemes under 1 MW, mostly rooftop solar (30)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sainsburys Supermarket, Barlborough Avenuerooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Dec 2025granted Feb 2026Mar 2026Stockton-on-Tees0.6
Fairfield Primary School, Glenfield Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Stockton-on-Tees1.5
Norton Substation, Letch Lanebattery storagebattery storage—approved, not builtupdated Jan 2024Oct 2023granted Jan 2024Jan 2024Stockton-on-Tees1.9
Dunedin House,Columbia Driverooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Stockton-on-Tees2.7
California Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Feb 2026Jun 2022granted Mar 2023Feb 2026Stockton-on-Tees2.7
Endeavour Houserooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Stockton-on-Tees3.5
David Lloyd Club, Tees Barrage Wayrooftop solarrooftop solar0.5approved, not builtupdated Nov 2023Jul 2023granted Nov 2023Nov 2023Stockton-on-Tees3.6
Motorpoint, Yarm Road Solar photovoltaics panelsrooftop solarrooftop solar0.2approved, not builtupdated May 2022May 2022granted Jul 2022May 2022Stockton-on-Tees3.7
Armadillo Self Storage, North Tees Industrial Estaterooftop solarrooftop solar0.1approved, not builtupdated Jun 2025May 2025granted May 2025Jun 2025Stockton-on-Tees4.5
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Jul 2022Jun 2022granted Nov 2022Jul 2022Stockton-on-Tees4.7
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagesolar farmsolar farm—approved, not built may be out of dateupdated Jul 2022Jul 2022granted Nov 2022Jul 2022Stockton-on-Tees4.7
Gately Moor Reservoir, Redmarshall Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Jul 2022Jul 2022granted Nov 2022Jul 2022Stockton-on-Tees4.7
The Forum Theatre, Town Centrerooftop solarrooftop solar—approved, not builtupdated Jun 2025Apr 2025granted Jun 2025Jun 2025Stockton-on-Tees4.8
Hollywood Bowl, Aintree Oval Solar Photovoltaics Panelsrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Dec 2024Feb 2025Middlesbrough4.9
Northfield School And Sports College, Thames Roadrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Stockton-on-Tees4.9
The North West & South East Sides Of The A19 Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Dec 2025Sep 2024granted Nov 2025Dec 2025Middlesbrough5.5
Riverside Park Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022Middlesbrough5.7
Sainsburys Supermarkets, Wynyard Retail Parkrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jul 2025granted Aug 2025Aug 2025Stockton-on-Tees6.2
Bulkhaul, Brignell Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2025Feb 2025granted Mar 2025May 2025Middlesbrough6.2
Riverside Park Industrial Estatebattery storagebattery storage0.2approved, not builtupdated Jun 2025Sep 2024granted May 2025Jun 2025Middlesbrough6.2
Zetland Multi Storey Car Park, Station Streetrooftop solarrooftop solar—approved, not builtupdated Nov 2022Aug 2022granted Sep 2022Nov 2022Middlesbrough6.8
Albert Road Rooftop Solar Panelsrooftop solarrooftop solar0.2operationalupdated Sep 2021Nov 2020granted Mar 2021Sep 2021Middlesbrough7.0
The Vale - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Jun 2025Sep 2024refused May 2025Jun 2025Middlesbrough7.3
Breckon Hill Primary School, Breckon Hill Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Middlesbrough8.0
Byers Gill Solar Farmbattery storagebattery storage—approved, not builtupdated Jul 2025Feb 2024granted Jul 2025Jul 2025Darlington8.6
Viewley Hill Academy, Andover Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Sep 2023granted Nov 2023Jan 2024Middlesbrough9.1
Cargo Fleet Lanerooftop solarrooftop solar0.2abandonedupdated Feb 2024Jun 2022—Feb 2024Middlesbrough9.1
Marton Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Dec 2025Aug 2025refused Oct 2025Dec 2025Middlesbrough9.3
Stainton Way - Micro Energy storagebattery storagebattery storage0.2application withdrawnupdated May 2025Sep 2024—May 2025Middlesbrough9.4
Huntsman Drive, Seal Sandsrooftop solarrooftop solar0.4application submittedMay 2026——Stockton-on-Tees9.6

Distance from the average position of the TS19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm120740461
Rooftop solar21118109.5
Wind farm600320
Wind turbine100000
Battery storage1501102180

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Teesside Offshore Wind Farm62operationalupdated May 201517.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Stockton-on-Tees decides solar, wind and battery applications

ApplicationsStockton-on-TeesUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 2012%
Onshore wind refused0 of 345%
Battery storage refused0 of 916%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Stockton-on-Tees

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TS19, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.