Energy Projects Near You

Belasis Avenue (75 MW battery storage)

Belasis Avenue is a 75 MW battery storage project in Stockton-on-Tees, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 April 2024, not yet built; the record was last updated on 26 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

75 MWbattery storage
approved, not builtstatus in REPD
26 August 2025record last updated
Stockton-on-Teescouncil area

Planning timeline

DateStage
29 August 2023Application submitted
19 April 2024Planning permission granted
19 April 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
75 MW
Status (REPD)
approved, not built
Record last updated
26 August 2025
Operator or applicant
Story Construction Limited
Planning authority
Stockton-on-Tees
Planning application reference
23/1634/FUL
Address (REPD)
South Side Of Belasis Avenue
Council area (by location)
Stockton-on-Tees
Time to decision
33 weeks
Name in REPD
Belasis Avenue - Battery Storage
REPD reference
13850

Who decides

ApplicationsStockton-on-TeesUK
Decided applications (solar, wind, battery)3210,236
Refused0 (0%)19%
Solar refused0 of 2012%
Onshore wind refused0 of 345%
Battery storage refused0 of 916%
Median time from submission to decision16.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Norton Bottomssolar farm5application withdrawn2.3
Land at Bluehouse Farmsolar farm5operational3.7
The Brick Bankbattery storage7permission expired3.7
Graythorp Wind Turbinewind turbine7.5application withdrawn5.9
Cowpen Bewley, Seal Sands Link Roadbattery storage200application submitted6.3
Tofts Road Wind Turbinewind turbine7.5application withdrawn6.4
Red Gap Moor Wind Farmwind farm12.5operational6.4
Brenda Road Wind Turbinewind turbine7.5application withdrawn6.5
Bowesfield Flexible Energy Parkbattery storage8approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.5994, -1.2639).