Energy Projects Near You

Land at Bluehouse Farm (5 MW solar farm)

Land at Bluehouse Farm is a 5 MW solar farm project in Hartlepool, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 August 2016; the record was last updated on 22 December 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
22 December 2016record last updated
Hartlepoolcouncil area

Planning timeline

DateStage
9 September 2015Application submitted
30 November 2015Planning permission granted
15 June 2016Construction started
31 August 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
22 December 2016
Operator or applicant
Anesco
Planning authority
Hartlepool
Planning application reference
H/2015/0316
Site area
11.1 ha
Address (REPD)
Land at Bluehouse Farm, Stockton Road, Newton Bewley, Billingham
Council area (by location)
Hartlepool
Time to decision
12 weeks
REPD reference
5656

Who decides

ApplicationsHartlepoolUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused1 of 1212%
Onshore wind refused0 of 345%
Battery storage refused0 of 316%
Median time from submission to decision32.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Belasis Avenuebattery storage75approved, not built3.7
Red Gap Moor Wind Farmwind farm12.5operational3.7
Brenda Road Wind Turbinewind turbine7.5application withdrawn4.1
Graythorp Wind Turbinewind turbine7.5application withdrawn4.2
Tofts Road Wind Turbinewind turbine7.5application withdrawn4.3
Norton Bottomssolar farm5application withdrawn5.6
High Barnes Farm, Coal Lane Solar Farmsolar farm49.9approved, not built6.5
High Barnes Farm, Coal Lanebattery storage25approved, not built6.5
Worset Lanebattery storage200approved, not built6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6326, -1.2684).