Butterwick Moor (20.5 MW wind farm)

Butterwick Moor is a 20.5 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2011; the record was last updated on 8 August 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.5 MWwind farm
operationalstatus in REPD
8 August 2011record last updated
County Durhamcouncil area

Planning timeline

DateStage
2 January 2007Application submitted
17 June 2007Planning permission granted
1 September 2010Construction started
1 April 2011Operational

Project details

Technology
wind farm
Capacity
20.5 MW
Status (REPD)
operational
Record last updated
8 August 2011
Operator or applicant
E.ON UK
Planning authority
County Durham
Planning application reference
7/2006/0796/DM
Turbines
10
Address (REPD)
Butterwick Moor , Sedgefield
Council area (by location)
County Durham
Time to decision
24 weeks
REPD reference
3218

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Walkwaywind farm14operational<0.1
Foxton Lanewind farm6refused5.2
Red Gap Moor Wind Farmwind farm12.5operational5.3
High Barnes Farm, Coal Lanebattery storage25approved, not built5.3
High Barnes Farm, Coal Lane Solar Farmsolar farm49.9approved, not built5.3
West House Farm, Fishburn Solar Farmsolar farm41.4approved, not built5.6
Cowley Complex, Stockton on Teessolar farm120under construction5.7
Sheraton Hall Solar Farmsolar farm49.9approved, not built6.1
Southern Lawwind farm5.2operational7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6636, -1.3969).