Sheraton Hall Solar Farm (49.9 MW)

Sheraton Hall Solar Farm is a 49.9 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 December 2023, not yet built; the record was last updated on 16 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
16 September 2025record last updated
County Durhamcouncil area

Planning timeline

DateStage
18 December 2020Application submitted
10 December 2021Refused by the planning authority
27 October 2022Appeal lodged
6 December 2023Planning permission granted
6 December 2023Appeal allowed
6 December 2026Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
16 September 2025
Operator or applicant
Lightsource BP
Planning authority
County Durham
Planning application reference
DM/20/03722/FPA
Appeal reference
22/00042/REF
Site area
77.4 ha
Address (REPD)
Sheraton Hall Farm
Council area (by location)
County Durham
Time to decision
155 weeks
Contracts for Difference
AR6
REPD reference
8254

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Sheraton Wind Farm (Durham)wind farm10refused1.7
Whelley Hill Farm, Worset Lanebattery storage50approved, not built2.1
Whelley Hill Farmbattery storage25application withdrawn2.1
High Volts Wind Farmwind farm5.5operational2.4
High Barnes Farm, Coal Lane Solar Farmsolar farm49.9approved, not built2.5
High Barnes Farm, Coal Lanebattery storage25approved, not built2.5
Home Farmsolar farm13abandoned2.7
Worset Lane Solar Farmsolar farm50approved, not built4.1
Benridge Farm, Fillpoke Lanesolar farm48application submitted4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7041, -1.3327).