Whelley Hill Farm (25 MW battery storage)

Whelley Hill Farm is a 25 MW battery storage project in Hartlepool, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 14 May 2019; the record was last updated on 14 May 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
application withdrawnstatus in REPD
14 May 2019record last updated
Hartlepoolcouncil area

Planning timeline

DateStage
16 January 2019Application submitted
14 May 2019Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
application withdrawn
Record last updated
14 May 2019
Operator or applicant
Volta Energy Storage
Planning authority
Hartlepool
Planning application reference
H/2018/0508
Address (REPD)
Whelley Hill Farm, Worset Lane, Hart, Hartlepool, Cleveland
Council area (by location)
Hartlepool
REPD reference
7296

Who decides

ApplicationsHartlepoolUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused1 of 1212%
Onshore wind refused0 of 345%
Battery storage refused0 of 316%
Median time from submission to decision32.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whelley Hill Farm, Worset Lanebattery storage50approved, not built<0.1
Home Farmsolar farm13abandoned0.6
High Volts Wind Farmwind farm5.5operational0.7
Worset Lane Solar Farmsolar farm50approved, not built2.0
Sheraton Hall Solar Farmsolar farm49.9approved, not built2.1
Sheraton Wind Farm (Durham)wind farm10refused2.3
High Barnes Farm, Coal Lane Solar Farmsolar farm49.9approved, not built2.3
High Barnes Farm, Coal Lanebattery storage25approved, not built2.3
Benridge Farm, Fillpoke Lanesolar farm48application submitted4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.6998, -1.3014).