Southern Law (5.2 MW wind farm)

Southern Law is a 5.2 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 July 2008; the record was last updated on 27 April 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.2 MWwind farm
operationalstatus in REPD
27 April 2009record last updated
County Durhamcouncil area

Planning timeline

DateStage
13 August 2004Application submitted
1 July 2005Planning permission granted
1 September 2007Construction started
10 July 2008Operational

Project details

Technology
wind farm
Capacity
5.2 MW
Status (REPD)
operational
Record last updated
27 April 2009
Operator or applicant
EDF Energy
Planning authority
County Durham
Planning application reference
4/04/958
Turbines
4
Address (REPD)
Southern Law Farm Trimdon Grange
Council area (by location)
County Durham
Time to decision
46 weeks
REPD reference
3223

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Trimdon Grangewind farm5.2operational0.5
Low Raisby Farm, Kelloesolar farm25.3application submitted1.6
Hawthorn Pit Green Energy Parkbattery storage1,000application submitted4.0
Edder Acres Farmwind farm5refused on appeal4.3
West House Farm, Fishburn Solar Farmsolar farm41.4approved, not built4.3
Harehill Farm, Haswell Plough Solar Farm & Battery Energy Storagesolar farm31.5refused4.8
Haswell Moorwind farm10operational5.1
Bowburnsolar farm5permission expired6.1
Spennymoor Greener Grid Parkbattery storage200approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7222, -1.4349).