Energy Projects Near You

Bowburn (5 MW solar farm)

Bowburn is a 5 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 15 February 2019; the record was last updated on 18 November 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
18 November 2019record last updated
County Durhamcouncil area

Planning timeline

DateStage
23 December 2015Application submitted
15 February 2017Planning permission granted
15 February 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
18 November 2019
Operator or applicant
Citrus Durham
Planning authority
County Durham
Planning application reference
DM/15/03912/OUT
Site area
4.0 ha
Address (REPD)
Land South Of, Bowburn, Durham
Council area (by location)
County Durham
Time to decision
60 weeks
REPD reference
6104

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Croxdale Farms, Hett Moor Farm Solar Farmsolar farm49.9approved, not built2.6
Spennymoor Greener Grid Parkbattery storage200approved, not built2.6
South Thinford Lane, Thinfordbattery storage99.9approved, not built3.4
Low Raisby Farm, Kelloesolar farm25.3application submitted4.8
Trimdon Grangewind farm5.2operational5.7
West House Farm, Fishburn Solar Farmsolar farm41.4approved, not built5.9
Southern Lawwind farm5.2operational6.1
Harehill Farm, Haswell Plough Solar Farm & Battery Energy Storagesolar farm31.5refused7.9
Hawthorn Pit Green Energy Parkbattery storage1,000application submitted8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7315, -1.529).