Energy Projects Near You

Low Raisby Farm, Kelloe (25.3 MW solar farm)

Low Raisby Farm, Kelloe is a 25.3 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 13 January 2026, no decision recorded; the record was last updated on 5 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25.3 MWsolar farm
application submittedstatus in REPD
5 February 2026record last updated
County Durhamcouncil area

Planning timeline

DateStage
13 January 2026Application submitted

Project details

Technology
solar farm
Capacity
25.3 MW
Status (REPD)
application submitted
Record last updated
5 February 2026
Operator or applicant
ABEI Energy Green II
Planning authority
County Durham
Planning application reference
DM/26/00070/FPA
Site area
33.6 ha
Address (REPD)
Low Raisby Farm, Kelloe, Durham
Council area (by location)
County Durham
Name in REPD
Low Raisby Farm, Kelloe - Solar Panels
REPD reference
19724

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Trimdon Grangewind farm5.2operational1.1
Southern Lawwind farm5.2operational1.6
West House Farm, Fishburn Solar Farmsolar farm41.4approved, not built3.2
Bowburnsolar farm5permission expired4.8
Spennymoor Greener Grid Parkbattery storage200approved, not built5.3
Hawthorn Pit Green Energy Parkbattery storage1,000application submitted5.3
Edder Acres Farmwind farm5refused on appeal5.8
Harehill Farm, Haswell Plough Solar Farm & Battery Energy Storagesolar farm31.5refused5.8
Croxdale Farms, Hett Moor Farm Solar Farmsolar farm49.9approved, not built6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7172, -1.4581).