Energy Projects Near You

Spennymoor Greener Grid Park (200 MW battery storage)

Spennymoor Greener Grid Park is a 200 MW battery storage project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 July 2025, not yet built; the record was last updated on 19 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
19 June 2026record last updated
County Durhamcouncil area

Planning timeline

DateStage
24 March 2023Application submitted
14 July 2025Planning permission granted
14 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
19 June 2026
Operator or applicant
Statkraft UK Limited
Planning authority
County Durham
Planning application reference
DM/23/00745/FPA
Address (REPD)
E/O Spennymoor, National Grid Station, Thinford Lane, Thinford, Durham
Council area (by location)
County Durham
Time to decision
120 weeks
REPD reference
13576

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Croxdale Farms, Hett Moor Farm Solar Farmsolar farm49.9approved, not built1.0
South Thinford Lane, Thinfordbattery storage99.9approved, not built1.2
Bowburnsolar farm5permission expired2.6
West House Farm, Fishburn Solar Farmsolar farm41.4approved, not built4.7
Low Raisby Farm, Kelloesolar farm25.3application submitted5.3
Trimdon Grangewind farm5.2operational6.3
Southern Lawwind farm5.2operational6.8
The Isles Wind Farmwind farm48application withdrawn9.7
Harehill Farm, Haswell Plough Solar Farm & Battery Energy Storagesolar farm31.5refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7085, -1.5385).