Solar, wind and battery projects near Durham (DH1)
33 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DH1 (County Durham): 4 are waiting for a planning decision, 18 approved but not yet running, 5 operational. The largest live scheme is Spennymoor Greener Grid Park (200 MW battery storage, approved on 14 July 2025, not yet built), 8.4 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Teesside Offshore Wind Farm (62 MW, operational), 33.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DH1
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bowburnsolar farm | solar farm | 5 | permission expiredupdated Nov 2019 | Dec 2015 | granted Feb 2017 | Nov 2019 | County Durham | 6.1 |
| Lumley Water Treatment Workssolar farm | solar farm | 1.9 | operationalupdated Jan 2022 | Oct 2020 | granted Dec 2020 | Jan 2022 | County Durham | 6.5 |
| Amazon UK Services - Photovoltaic Systemrooftop solar | rooftop solar | 3.5 | approved, not built may be out of dateupdated Aug 2024 | Jan 2022 | granted Apr 2022 | Aug 2024 | County Durham | 6.7 |
| MME3, Plot DC1, Integra 61wind turbine | wind turbine | 2.3 | application submittedupdated Jun 2025 | Apr 2025 | — | Jun 2025 | County Durham | 6.9 |
| Old Quarrington (A)wind farm | wind farm | 2 | refusedupdated Nov 2004 | Jun 2002 | refused Aug 2002 | Nov 2004 | County Durham | 7.1 |
| Old Quarrington (B)wind farm | wind farm | 2 | refusedupdated Nov 2004 | Jun 2002 | refused Nov 2002 | Nov 2004 | County Durham | 7.1 |
| Croxdale Farms, Hett Moor Farm Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Dec 2024 | Jun 2023 | granted Nov 2024 | Dec 2024 | County Durham | 7.8 |
| Spennymoor Greener Grid Parkbattery storage | battery storage | 200 | approved, not builtupdated Jun 2026 | Mar 2023 | granted Jul 2025 | Jun 2026 | County Durham | 8.4 |
| Langley Moorwind farm | wind farm | 8 | operationalupdated Apr 2009 | Jan 2005 | granted Jun 2005 | Apr 2009 | County Durham | 8.5 |
| Thorn Lighting, Butchers Racerooftop solar | rooftop solar | 1.7 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 | County Durham | 8.6 |
| South Thinford Lane, Thinfordbattery storage | battery storage | 99.9 | approved, not built may be out of dateupdated Jan 2022 | Jan 2022 | granted Oct 2022 | Jan 2022 | County Durham | 8.6 |
| High Haswell Wind Farmwind farm | wind farm | 4 | operationalupdated Apr 2011 | Apr 2007 | granted Dec 2007 | Apr 2011 | County Durham | 8.6 |
| Harehill Farm, Haswell Plough Solar Farm & Battery Energy Storagesolar farm | solar farm | 31.5 | refusedupdated Jul 2025 | Dec 2024 | refused Jul 2025 | Jul 2025 | County Durham | 9.5 |
| Harehill Farm, Haswell Plough Solar Farm & Battery Energy Storagebattery storage | battery storage | 10.3 | refusedupdated Jul 2025 | Dec 2024 | refused Jul 2025 | Jul 2025 | County Durham | 9.5 |
| Hare Hill (B)wind farm | wind farm | 2.7 | operationalupdated May 2013 | Apr 1994 | granted Mar 1997 | May 2013 | County Durham | 9.9 |
| Hare Hillwind turbine | wind turbine | 1.3 | operationalupdated May 2009 | Feb 2000 | granted May 2000 | May 2009 | County Durham | 9.9 |
| Low Raisby Farm, Kelloesolar farm | solar farm | 25.3 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | County Durham | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Durham Gilesgate Primary School, Kepier Crescentrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Dec 2025 | Oct 2025 | — | Dec 2025 | County Durham | 1.1 |
| SG Petch, Broomside Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | County Durham | 1.4 |
| The Graham Sports Centre, Maiden Castlerooftop solar | rooftop solar | — | approved, not builtupdated Sep 2023 | Aug 2023 | granted Sep 2023 | Sep 2023 | County Durham | 1.7 |
| Faerch Durham Solar Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jun 2021 | Jun 2021 | granted Jul 2021 | Jun 2021 | County Durham | 1.8 |
| University Hospitalrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | County Durham | 2.0 |
| Grey College, South Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Aug 2023 | granted Sep 2023 | Sep 2023 | County Durham | 2.0 |
| Collingwood College, South Roadrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | County Durham | 2.3 |
| Belmont Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | County Durham | 2.3 |
| Josephine Butler College Main Building, South Roadrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | County Durham | 2.6 |
| Boldon House, Wheatlands Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Apr 2024 | granted May 2024 | May 2024 | County Durham | 3.0 |
| Porch House Farm, East Streetbattery storage | battery storage | — | application submittedupdated May 2025 | Apr 2025 | — | May 2025 | County Durham | 6.5 |
| Evolve Business Centrerooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Oct 2023 | Feb 2020 | granted May 2020 | Oct 2023 | Sunderland | 7.6 |
| Evolve Business Centrebattery storage | battery storage | — | approved, not built may be out of dateupdated Jan 2022 | Feb 2020 | granted May 2020 | Jan 2022 | Sunderland | 7.6 |
| Chester-Le-Street Community Hospitalrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Dec 2025 | granted Feb 2026 | Jan 2026 | County Durham | 7.7 |
| Hetton Commnity Pool/Wellness Centre, Welfare Roadrooftop solar | rooftop solar | 0.2 | application submittedupdated Sep 2024 | Sep 2024 | — | Sep 2024 | Sunderland | 8.4 |
| Sedgeletch Sewage Treatment Workssolar farm | solar farm | — | under constructionupdated Oct 2022 | Nov 2020 | granted Jan 2021 | Oct 2022 | Sunderland | 8.9 |
Distance from the average position of the DH1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 1 | 2 | 1 | 1 | 75.2 |
| Rooftop solar | 15 | 1 | 13 | 0 | 0 | 7.5 |
| Wind farm | 5 | 0 | 0 | 3 | 2 | 0 |
| Wind turbine | 2 | 1 | 0 | 1 | 0 | 2.3 |
| Battery storage | 5 | 1 | 3 | 0 | 1 | 300 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Teesside Offshore Wind Farm | 62 | operationalupdated May 2015 | 33.8 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How County Durham decides solar, wind and battery applications
| Applications | County Durham | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 22 (25%) | 19% |
| Solar refused | 7 of 51 | 12% |
| Onshore wind refused | 13 of 30 | 45% |
| Battery storage refused | 2 of 8 | 16% |
| Median time from submission to decision | 24.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 5 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DH1, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.