Langley Moor (8 MW wind farm)

Langley Moor is an 8 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 13 August 2008; the record was last updated on 27 April 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
operationalstatus in REPD
27 April 2009record last updated
County Durhamcouncil area

Planning timeline

DateStage
28 January 2005Application submitted
30 June 2005Planning permission granted
13 August 2008Operational

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
27 April 2009
Operator or applicant
EDF Energy
Planning authority
County Durham
Planning application reference
not recorded
Turbines
4
Address (REPD)
Burnhope Standagainstall Plantation, Long Edge, Burnhope, County Durham
Council area (by location)
County Durham
Time to decision
22 weeks
REPD reference
3248

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Edge Lane, Maiden Law Solar Farm & Battery Storagesolar farm49.9approved, not built3.3
Wagtail Lane, Cragheadsolar farm27refused3.6
Maiden, Annfield Plainbattery storage38approved, not built4.6
Green Croft Solar Farmsolar farm5operational4.7
High Hedley Hope 2 (Extension)wind farm5.2operational8.5
Broom Hill Farmwind farm8operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8237, -1.6758).