Energy Projects Near You

Edge Lane, Maiden Law Solar Farm & Battery Storage (49.9 MW)

Edge Lane, Maiden Law Solar Farm & Battery Storage is a 49.9 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 April 2026, not yet built; the record was last updated on 8 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
8 June 2026record last updated
County Durhamcouncil area

Planning timeline

DateStage
30 June 2022Application submitted
10 March 2025Refused by the planning authority
24 June 2025Appeal lodged
22 April 2026Planning permission granted
22 April 2026Appeal allowed
22 April 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
8 June 2026
Operator or applicant
Lightsource BP
Planning authority
County Durham
Planning application reference
DM/22/01769/FPA
Appeal reference
25/00027/REF
Site area
91.7 ha
Address (REPD)
East Of Edge Lane Maiden Law
Council area (by location)
County Durham
Time to decision
199 weeks
Name in REPD
Edge Lane, Maiden Law - Solar Farm & Battery Storage
REPD reference
11618

The scheme also includes 45 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Croft Solar Farmsolar farm5operational1.6
Maiden, Annfield Plainbattery storage38approved, not built1.6
Wagtail Lane, Cragheadsolar farm27refused2.4
Langley Moorwind farm8operational3.3
Hownsgill Industrial Parksolar farm5under construction7.5
High Hedley Hope 2 (Extension)wind farm5.2operational8.2
Broom Hill Farmwind farm8operational9.7
West Durham Wind Farmwind farm24operational9.8
Hedley Hope, Tow Lawwind farm31.5application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.835, -1.7242).