Energy Projects Near You

Green Croft Solar Farm (5 MW)

Green Croft Solar Farm is a 5 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 December 2016; the record was last updated on 1 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 February 2017record last updated
County Durhamcouncil area

Planning timeline

DateStage
23 July 2015Application submitted
4 November 2015Planning permission granted
7 October 2016Construction started
7 December 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 February 2017
Operator or applicant
Anesco
Planning authority
County Durham
Planning application reference
DM/15/02279/FPA
Site area
11.1 ha
Address (REPD)
Land Between Greencroft Indust, Tower Road/Lanchester Road, Greencroft, Stanley, County Durham
Council area (by location)
County Durham
Time to decision
15 weeks
REPD reference
5380

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Maiden, Annfield Plainbattery storage38approved, not built0.3
Edge Lane, Maiden Law Solar Farm & Battery Storagesolar farm49.9approved, not built1.6
Wagtail Lane, Cragheadsolar farm27refused2.2
Langley Moorwind farm8operational4.7
Hownsgill Industrial Parksolar farm5under construction6.8
Greenhead Energy Parksolar farm49.9application submitted8.9
High Hedley Hope 2 (Extension)wind farm5.2operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8476, -1.7367).