Energy Projects Near You

Solar, wind and battery projects near Rowlands Gill (NE39)

43 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE39 (Gateshead): 6 are waiting for a planning decision, 28 approved but not yet running, 3 operational. The largest live scheme is Newburn Bridge Road (100 MW battery storage, approved on 31 March 2022, not yet built; REPD status may be out of date), 5.9 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 37.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43projects within 10 km
6awaiting a decision
28approved, not running
3operational

Projects within 10 km of NE39

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Greenhead Energy Parksolar farmsolar farm49.9application submitted may be out of dateupdated Jun 2024May 2024—Jun 2024Gateshead3.8
Greenhead Energy Parkbattery storagebattery storage13application submitted may be out of dateupdated Jun 2024May 2024—Jun 2024Gateshead3.8
Comeleon House Solar PV Farmsolar farmsolar farm4abandonedupdated Jun 2016May 2015granted Jun 2015Jun 2016County Durham5.9
Newburn Bridge Roadbattery storagebattery storage100approved, not built may be out of dateupdated Oct 2024Aug 2021granted Mar 2022Oct 2024Gateshead5.9
Land at Derwenthaugh Eco Parkbattery storagebattery storage29permission expiredupdated May 2020Mar 2018granted Nov 2018May 2020Gateshead6.4
Newburn BESSbattery storagebattery storage90application submitted may be out of dateupdated Jul 2024May 2024—Jul 2024Newcastle upon Tyne6.7
Morris Marble Works, Cross Lanebattery storagebattery storage100application withdrawnupdated Dec 2025Jul 2025—Dec 2025Gateshead7.5
Number One Industrial Estaterooftop solarrooftop solar1approved, not built may be out of dateupdated Mar 2022Feb 2022granted Apr 2022Mar 2022County Durham7.8
Greencroft Estate Turbineswind farmwind farm4operationalupdated Jul 2013Jun 2011granted Nov 2011Jul 2013County Durham8.3
Maiden, Annfield Plainbattery storagebattery storage38approved, not builtupdated Jul 2022May 2021granted Aug 2021Jul 2022County Durham8.5
Green Croft Solar Farmsolar farmsolar farm5operationalupdated Feb 2017Jul 2015granted Nov 2015Feb 2017County Durham8.6
Parker Hannifin Manufacturingrooftop solarrooftop solar1.1approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Gateshead8.7
Wagtail Lane, Cragheadsolar farmsolar farm27refusedupdated Jan 2026Jan 2025refused Dec 2025Jan 2026County Durham8.8
Highfield Energy Parksolar farmsolar farm40appeal lodged may be out of dateupdated Jan 2026May 2023refused Aug 2025Jan 2026Northumberland9.4
Highfield Energy Parkbattery storagebattery storage12.5appeal lodged may be out of dateupdated Jan 2026May 2023refused Aug 2025Jan 2026Northumberland9.4
Smaller schemes under 1 MW, mostly rooftop solar (28)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Gas Governor Station Solar Systemsolar farmsolar farm0.3approved, not built may be out of dateupdated Jan 2022Nov 2020granted Apr 2022Jan 2022Gateshead2.9
Bailey House, Stargate Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026Gateshead4.6
Harelaw Industrial Estaterooftop solarrooftop solar0.9approved, not builtupdated Oct 2023Jul 2023granted Oct 2023Oct 2023County Durham5.6
Newburn Haugh Battery Storage Systemcbattery storagebattery storage—approved, not builtupdated Jul 2025Aug 2023granted Jun 2025Jul 2025Newcastle upon Tyne6.3
Warburtons, Shelley Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Newcastle upon Tyne6.4
Shelley Roadbattery storagebattery storage—refusedupdated Nov 2018Oct 2017refused Dec 2017Nov 2018Newcastle upon Tyne6.5
South Causey Inn, Causey Roadsolar farmsolar farm0.2refusedupdated Mar 2024Sep 2023refused Mar 2024Mar 2024County Durham6.5
Union Hall Road, Lemingtonbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2023Aug 2022granted Jan 2023Feb 2023Newcastle upon Tyne6.9
Metrocentre Green Car Park, St Michaels Way - Photovoltaic Equipmentsolar farmsolar farm—under constructionupdated Sep 2022Dec 2021granted Jan 2023Sep 2022Gateshead6.9
Metrocentre, St Michaels Wayrooftop solarrooftop solar0.7approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Gateshead7.0
Salem Tubes, Regents Drive Solar PV Equipmentrooftop solarrooftop solar0.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Northumberland7.1
Excelsior Academy, Denton Roadrooftop solarrooftop solar0.5under constructionupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Newcastle upon Tyne7.3
Dunston Leisure Centre, Dunston Bankrooftop solarrooftop solar0.2approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025Gateshead7.6
Paradise Works, Scotswood Road - Photovoltaic Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Newcastle upon Tyne7.7
Number One Industrial Estaterooftop solarrooftop solar0.3approved, not builtupdated Dec 2021Oct 2021granted Nov 2021Dec 2021County Durham7.9
Walbottle Campus Technology Collegerooftop solarrooftop solar0.5approved, not builtupdated Sep 2021Apr 2021granted Jun 2021Sep 2021Newcastle upon Tyne8.2
Hadrian School, Bertram Crescentrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Newcastle upon Tyne8.4
Canning Street Primary School - Photovoltaic Panelsrooftop solarrooftop solar—approved, not builtupdated May 2021Apr 2021granted Jun 2021May 2021Newcastle upon Tyne8.6
Dacon Fabrications Limited, Dukeswayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Oct 2022granted Nov 2022Nov 2022Gateshead8.7
West Denton Leisure Centre - Photovoltaic Panelsrooftop solarrooftop solar0.2approved, not builtupdated Sep 2021Aug 2021granted Sep 2021Sep 2021Newcastle upon Tyne8.8
West Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2021Aug 2021granted Sep 2021Sep 2021Newcastle upon Tyne8.8
Monkhouse And Brown, Team Streetrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jun 2025Jul 2025Gateshead8.8
Sanderson Street - Photovoltaic panelsrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Newcastle upon Tyne8.9
Arnold Clark Seat & Body Shop, Gardener Streetrooftop solarrooftop solar0.2application submittedJun 2026——Newcastle upon Tyne9.0
Derwentside Environmental Testing Servs Limitedrooftop solarrooftop solar0.4operationalupdated Sep 2024May 2024granted Sep 2024Sep 2024County Durham9.2
Team Valley Trading Estate Solar Photovoltaic Equipmentrooftop solarrooftop solar0.2approved, not builtupdated Feb 2022Feb 2022granted Mar 2022Feb 2022Gateshead9.3
Riverdale Paper, Earlswayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Oct 2022granted Nov 2022Nov 2022Gateshead9.4
Stamfordham Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2021Aug 2021granted Oct 2021Oct 2021Newcastle upon Tyne9.6

Distance from the average position of the NE39 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8221290.2
Rooftop solar24122108.6
Wind farm100100
Battery storage103401254

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Blyth Offshore Wind Test Site41.5operationalupdated Jul 201837.0
Blyth Offshore Wind Farm Phase 2 Demonstrator Project58.4approved, not builtupdated Apr 202237.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Gateshead decides solar, wind and battery applications

ApplicationsGatesheadUK
Decided applications (solar, wind, battery)2310,236
Refused1 (4%)19%
Solar refused0 of 2012%
Battery storage refused1 of 316%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Gateshead

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE39, 9 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.