Blyth Offshore Wind Test Site offshore wind farm

Blyth Offshore Wind Test Site is a 41.5 MW offshore wind farm with 5 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 October 2017; the record was last updated on 4 July 2018. Its REPD grid reference is 9 km from the nearest postcode on land (NE64 6DP, Northumberland). REPD names the Marine Management Organisation as the consenting authority.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

41.5 MWoffshore wind farm
operationalstatus in REPD
4 July 2018record last updated
9 km from land (Northumberland)REPD location

Consent timeline

DateStage
1 March 2012Application submitted
8 November 2013Consent granted (Marine Management Organisation)
22 October 2016Construction started
22 October 2017Operational

Project details

Technology
offshore wind farm
Capacity
41.5 MW
Turbines
5
Turbine capacity
8.3 MW
Status (REPD)
operational
Record last updated
4 July 2018
Operator or applicant
EDF Energy Renewables
Consenting authority (REPD)
Marine Management Organisation
Application reference
not recorded
Nearest postcode on land
NE64 6DP (Northumberland), 9.1 km from the REPD grid reference
Time to decision
88 weeks
Name in REPD
Blyth Offshore Wind Test Site
REPD reference
2523

Who decides

REPD names the Marine Management Organisation as the consenting authority.

Postcode districts within 40 km

Districtkm
Newbiggin-by-the-Sea (NE64)9.8
Blyth (NE24)11.3
Ashington (NE63)12.6
Whitley Bay (NE26)14.0
Choppington (NE62)14.6
Bedlington (NE22)14.6
Whitley Bay (NE25)15.0
North Shields (NE30)16.9
Cramlington (NE23)17.0
Newcastle upon Tyne (NE27)17.7
North Shields (NE29)18.4
South Shields (NE33)20.0

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Blyth Offshore Wind Farm Phase 2 Demonstrator Project58.4approved, not built<0.1
Blyth Offshore4decommissioned8.7

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (55.167, -1.3644).