Solar, wind and battery projects near Newcastle upon Tyne (NE27)
82 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE27 (North Tyneside): 10 are waiting for a planning decision, 65 approved but not yet running, 3 operational. The largest live scheme is Church Bank (100 MW battery storage, application submitted on 5 September 2025, no decision recorded), 6.6 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 17.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NE27
Projects of 1 MW and more (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Tynemouth Energy Storage System (TESS)battery storage | battery storage | 25 | operationalupdated Aug 2018 | Sep 2016 | — | Aug 2018 | North Tyneside | 1.1 |
| Backworth Lane, Backworth Solar Farmsolar farm | solar farm | 28 | approved, not built may be out of dateupdated Oct 2024 | Nov 2022 | granted May 2023 | Oct 2024 | North Tyneside | 2.7 |
| Seghill Household Waste Recovery Centre -Solar Panelssolar farm | solar farm | 5.8 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Northumberland | 3.6 |
| Seghill Household Waste Recovery Centresolar farm | solar farm | 5.8 | application submittedupdated Feb 2026 | Dec 2025 | — | Feb 2026 | Northumberland | 3.6 |
| Standby Embedded Stor Power Plantbattery storage | battery storage | 20 | under constructionupdated Jan 2023 | Apr 2021 | granted Jun 2021 | Jan 2023 | North Tyneside | 3.9 |
| Benton Lane, Quorum Business Parksolar farm | solar farm | 8 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | North Tyneside | 4.6 |
| Mylord Crescent, Camperdown Industrial Estate, Unit 12rooftop solar | rooftop solar | 1.4 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | North Tyneside | 4.8 |
| A&P Tynewind turbine | wind turbine | 2 | permission expiredupdated Jun 2015 | Feb 2008 | granted Apr 2009 | Jun 2015 | South Tyneside | 5.4 |
| Church Bankbattery storage | battery storage | 100 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | South Tyneside | 6.6 |
| Aesica Pharmaceuticalswind farm | wind farm | 6 | refusedupdated Apr 2011 | May 2006 | refused Feb 2007 | Apr 2011 | Northumberland | 7.1 |
| Port of Tynebattery storage | battery storage | 35 | operationalupdated May 2019 | Sep 2016 | — | May 2019 | South Tyneside | 7.2 |
| Low Hortonbattery storage | battery storage | 50 | approved, not builtupdated Jan 2025 | Aug 2024 | granted Jan 2025 | Jan 2025 | Northumberland | 7.6 |
| Renolit Cramlington Limited, Station Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | Northumberland | 8.8 |
| Albany Roadsolar farm | solar farm | 2 | approved, not built may be out of dateupdated Dec 2022 | Oct 2021 | granted Dec 2021 | Dec 2022 | Gateshead | 8.9 |
| Low Horton Farm Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Sep 2021 | Apr 2022 | granted Nov 2022 | Sep 2021 | Northumberland | 9.1 |
| Responsive Engineering, Scotswood Roadrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle upon Tyne | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (60)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Whitley Road, Holystonebattery storage | battery storage | — | application withdrawnupdated Jun 2026 | Aug 2022 | — | Jun 2026 | North Tyneside | 0.8 |
| Tynemouth Substationbattery storage | battery storage | — | application withdrawnupdated May 2026 | Aug 2024 | — | May 2026 | North Tyneside | 1.2 |
| Unit A, Merlin Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | North Tyneside | 1.4 |
| Unit C, Merlin Wayrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | North Tyneside | 1.5 |
| Unit B, Merlin Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Nov 2023 | Dec 2023 | North Tyneside | 1.6 |
| North Tyneside General Hospitalrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Nov 2021 | Nov 2021 | North Tyneside | 3.1 |
| Venus Park, Trading Estatebattery storage | battery storage | — | approved, not builtupdated Mar 2024 | Jul 2022 | granted Sep 2022 | Mar 2024 | North Tyneside | 3.5 |
| Seghill Household Waste Recovery Centrebattery storage | battery storage | — | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Northumberland | 3.6 |
| Seghill Household Waste Recovery Centrebattery storage | battery storage | — | application submittedupdated Feb 2026 | Dec 2025 | — | Feb 2026 | Northumberland | 3.6 |
| Hamar Close & Wallsend Road, High Flatworthbattery storage | battery storage | — | approved, not builtupdated Oct 2024 | Apr 2023 | granted Sep 2024 | Oct 2024 | North Tyneside | 3.9 |
| Planet Place, Stephenson Industrial Estate - Unit 27 - Battery Energy Storagebattery storage | battery storage | — | application submittedupdated Jun 2025 | Apr 2025 | — | Jun 2025 | North Tyneside | 4.0 |
| Quorum Building, Benton Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | North Tyneside | 4.6 |
| Soil Machine Dynamic, Davy Bankrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Feb 2024 | granted Feb 2024 | Mar 2024 | North Tyneside | 4.9 |
| Corchester Walk Solar Photovoltaic Panels & Air Sourced Heat Pumpsrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2022 | Jan 2022 | granted May 2022 | Jan 2022 | Newcastle upon Tyne | 5.2 |
| Armadillo Self Storage, Heatonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | Newcastle upon Tyne | 5.3 |
| Clarendon, Windmill Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | South Tyneside | 5.4 |
| Viking Energy Network, Blackett Street - Turbine Repoweringwind turbine | wind turbine | 0.8 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | South Tyneside | 5.5 |
| Benfield School, Benfield Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 5.5 |
| Benfield School, Benfield Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 5.5 |
| Border Control Post, Coble Denerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | North Tyneside | 6.0 |
| YHN House, Benton Park Road- Solar Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2022 | Nov 2021 | granted Dec 2021 | Jan 2022 | Newcastle upon Tyne | 6.0 |
| Sterling Pharma Solutionsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | North Tyneside | 6.0 |
| Benfield Business Park, Benfield Road -Solar Panelsrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Jul 2024 | Aug 2024 | Newcastle upon Tyne | 6.1 |
| Walker Riverside Academy - Photovoltaic Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2021 | Apr 2021 | granted Jun 2021 | Jun 2021 | Newcastle upon Tyne | 6.1 |
| Walkergate Primary School - Photovoltaic Panelsrooftop solar | rooftop solar | — | approved, not builtupdated May 2021 | Apr 2021 | granted Jun 2021 | May 2021 | Newcastle upon Tyne | 6.1 |
| Ravenswood Primary School, Ravenswood Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 6.1 |
| David Lloyd Leisure, Castles Farm Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Newcastle upon Tyne | 6.4 |
| Tyneview Primary School, Winslow Placerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 6.7 |
| Hebburn Lakes Primary School, Campbell Park Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | South Tyneside | 6.7 |
| UTS Engineering, Pilgrimswayrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | South Tyneside | 7.1 |
| North Gosforth Academy, Dudley Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | North Tyneside | 7.2 |
| Port Of Tyne, Tyne Dockbattery storage | battery storage | — | application submitted may be out of dateupdated Aug 2022 | Jul 2022 | — | Aug 2022 | South Tyneside | 7.2 |
| Gosforth Academy, Knightsbridgerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Sep 2023 | Oct 2023 | Newcastle upon Tyne | 7.3 |
| Gosforth Academyrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Newcastle upon Tyne | 7.3 |
| Dunes Amusement Arcade, Sea Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | South Tyneside | 7.3 |
| Simonside Industrial Unit, Shaftesbury Avenuerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2024 | Sep 2024 | granted Oct 2024 | Oct 2024 | South Tyneside | 7.3 |
| Westoe Crown Primary School, Sea Winnings Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | South Tyneside | 7.3 |
| Merchant House Warehouse, Tyne Dock Solar Photovoltaics Equipmentrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2023 | Sep 2023 | granted Nov 2023 | Dec 2023 | South Tyneside | 7.4 |
| Hadrian Square - Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2021 | Aug 2021 | granted Sep 2021 | Oct 2021 | Newcastle upon Tyne | 7.4 |
| Grange First School, Norham Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 7.5 |
| Unit 1, Walker Riverside, Wincomblee Road -Photovoltaic Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Newcastle upon Tyne | 7.7 |
| Middlefields Depot, Middlefields Industrial Estaterooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Feb 2026 | Apr 2026 | South Tyneside | 7.7 |
| Newington Road West Depotrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Dec 2021 | granted Feb 2022 | Feb 2022 | Newcastle upon Tyne | 7.8 |
| Mortimer community college, Reading Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | South Tyneside | 8.0 |
| Welford Day Centre, Jubilee Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Jul 2023 | granted Aug 2023 | Oct 2023 | Newcastle upon Tyne | 8.0 |
| Saint Nicholas Hospital, Jubilee Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle upon Tyne | 8.1 |
| Royal Grammar School, Eskdale Terracerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Newcastle upon Tyne | 8.1 |
| Brunton First School, Roseden Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Newcastle upon Tyne | 8.1 |
| Ouseburn Trust, Lime Street Solar Panels & ASHPsrooftop solar | rooftop solar | 0.3 | application submitted | May 2026 | — | — | Newcastle upon Tyne | 8.1 |
| Newcastle University, Robinson Libraryrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Feb 2022 | granted Mar 2022 | Feb 2022 | Newcastle upon Tyne | 8.4 |
| Students Union Buildingrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Feb 2022 | Feb 2022 | granted Apr 2022 | Feb 2022 | Newcastle upon Tyne | 8.8 |
| Newcastle University, Boiler House - Roof Mounted Photovoltaic Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Aug 2023 | Jul 2023 | granted Aug 2023 | Aug 2023 | Newcastle upon Tyne | 8.8 |
| Donwood Double Glazing, Stonehills Buildings - Unit A23 - Solar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Gateshead | 8.8 |
| Robert Duncan Timber Limited, Green Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Jan 2023 | Feb 2023 | Gateshead | 8.9 |
| Newcastle University Sports Centrerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Newcastle upon Tyne | 9.0 |
| Dame Margaret Barbour Building - Photovoltaic panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2021 | Jun 2021 | granted Aug 2021 | Jun 2021 | Newcastle upon Tyne | 9.0 |
| Bassington Industrial Estatebattery storage | battery storage | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jun 2025 | Aug 2025 | Northumberland | 9.0 |
| Neilson Roadsolar farm | solar farm | 0.9 | approved, not built may be out of dateupdated Feb 2022 | Oct 2021 | granted Dec 2021 | Feb 2022 | Gateshead | 9.1 |
| Browns 2000, Colbourne Avenuerooftop solar | rooftop solar | 1 | approved, not builtupdated Jul 2023 | Jan 2023 | granted Mar 2023 | Jul 2023 | Northumberland | 9.1 |
| Advanced Composite Engineering, Colbourne Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Feb 2023 | Feb 2023 | Northumberland | 9.2 |
6 more projects not listed (furthest or smallest).
Distance from the average position of the NE27 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 3 | 4 | 1 | 0 | 101 |
| Rooftop solar | 57 | 1 | 56 | 0 | 0 | 21.5 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Wind turbine | 2 | 1 | 0 | 0 | 0 | 0.8 |
| Battery storage | 14 | 5 | 5 | 2 | 0 | 170 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Blyth Offshore Wind Test Site | 41.5 | operationalupdated Jul 2018 | 17.7 |
| Blyth Offshore Wind Farm Phase 2 Demonstrator Project | 58.4 | approved, not builtupdated Apr 2022 | 17.7 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How North Tyneside decides solar, wind and battery applications
| Applications | North Tyneside | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 14 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 11 | 12% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 7.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in North Tyneside
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE27, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.