Energy Projects Near You

Solar, wind and battery projects near North Shields (NE29)

64 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE29 (North Tyneside): 11 are waiting for a planning decision, 48 approved but not yet running, 2 operational. The largest live scheme is Church Bank (100 MW battery storage, application submitted on 5 September 2025, no decision recorded), 3.7 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Blyth Offshore Wind Test Site (41.5 MW, operational), 18.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

64projects within 10 km
11awaiting a decision
48approved, not running
2operational

Projects within 10 km of NE29

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Standby Embedded Stor Power Plantbattery storagebattery storage20under constructionupdated Jan 2023Apr 2021granted Jun 2021Jan 2023North Tyneside1.4
Tynemouth Energy Storage System (TESS)battery storagebattery storage25operationalupdated Aug 2018Sep 2016—Aug 2018North Tyneside2.9
Church Bankbattery storagebattery storage100application submittedupdated Oct 2025Sep 2025—Oct 2025South Tyneside3.7
Port of Tynebattery storagebattery storage35operationalupdated May 2019Sep 2016—May 2019South Tyneside3.9
A&P Tynewind turbinewind turbine2permission expiredupdated Jun 2015Feb 2008granted Apr 2009Jun 2015South Tyneside4.5
Backworth Lane, Backworth Solar Farmsolar farmsolar farm28approved, not built may be out of dateupdated Oct 2024Nov 2022granted May 2023Oct 2024North Tyneside6.5
Seghill Household Waste Recovery Centre -Solar Panelssolar farmsolar farm5.8application submittedupdated Jan 2026Dec 2025—Jan 2026Northumberland7.3
Seghill Household Waste Recovery Centresolar farmsolar farm5.8application submittedupdated Feb 2026Dec 2025—Feb 2026Northumberland7.3
Benton Lane, Quorum Business Parksolar farmsolar farm8application submittedupdated May 2026Mar 2026—May 2026North Tyneside7.6
West Boldon Substationbattery storagebattery storage60approved, not builtupdated Jul 2025Jul 2023granted Dec 2024Jul 2025South Tyneside8.1
Mylord Crescent, Camperdown Industrial Estate, Unit 12rooftop solarrooftop solar1.4approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025North Tyneside8.5
E/o the Academy Of Light, Sunderland Road Solar Farmsolar farmsolar farm40application submitted may be out of dateupdated Jul 2024Jul 2024—Jul 2024South Tyneside9.0
NCL1, Follingsby Lanerooftop solarrooftop solar3.9approved, not built may be out of dateupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Gateshead9.0
Albany Roadsolar farmsolar farm2approved, not built may be out of dateupdated Dec 2022Oct 2021granted Dec 2021Dec 2022Gateshead9.5
SNOP UK, Washington Roadrooftop solarrooftop solar1.1approved, not builtupdated Feb 2026Jan 2026granted Mar 2026Feb 2026Sunderland9.8
Smaller schemes under 1 MW, mostly rooftop solar (49)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hamar Close & Wallsend Road, High Flatworthbattery storagebattery storage—approved, not builtupdated Oct 2024Apr 2023granted Sep 2024Oct 2024North Tyneside1.3
North Tyneside General Hospitalrooftop solarrooftop solar1approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021North Tyneside1.5
Venus Park, Trading Estatebattery storagebattery storage—approved, not builtupdated Mar 2024Jul 2022granted Sep 2022Mar 2024North Tyneside1.8
Border Control Post, Coble Denerooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025North Tyneside2.3
Unit B, Merlin Wayrooftop solarrooftop solar0.7approved, not builtupdated Dec 2023Oct 2023granted Nov 2023Dec 2023North Tyneside2.4
Unit C, Merlin Wayrooftop solarrooftop solar0.5approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023North Tyneside2.4
Unit A, Merlin Wayrooftop solarrooftop solar0.7approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023North Tyneside2.5
Tynemouth Substationbattery storagebattery storage—application withdrawnupdated May 2026Aug 2024—May 2026North Tyneside2.7
Dunes Amusement Arcade, Sea Roadrooftop solarrooftop solar0.1approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026South Tyneside3.4
Westoe Crown Primary School, Sea Winnings Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Nov 2025Jan 2026South Tyneside3.4
Port Of Tyne, Tyne Dockbattery storagebattery storage—application submitted may be out of dateupdated Aug 2022Jul 2022—Aug 2022South Tyneside3.9
UTS Engineering, Pilgrimswayrooftop solarrooftop solar—approved, not builtupdated Jan 2026Sep 2025granted Oct 2025Jan 2026South Tyneside3.9
Merchant House Warehouse, Tyne Dock Solar Photovoltaics Equipmentrooftop solarrooftop solar0.7approved, not builtupdated Dec 2023Sep 2023granted Nov 2023Dec 2023South Tyneside3.9
Viking Energy Network, Blackett Street - Turbine Repoweringwind turbinewind turbine0.8application submittedupdated May 2026Apr 2026—May 2026South Tyneside3.9
Mortimer community college, Reading Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Oct 2025granted Nov 2025Jan 2026South Tyneside4.1
Clarendon, Windmill Wayrooftop solarrooftop solar0.4approved, not builtupdated Jan 2026Sep 2025granted Oct 2025Jan 2026South Tyneside4.1
Middlefields Depot, Middlefields Industrial Estaterooftop solarrooftop solar0.5approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026South Tyneside4.2
Simonside Industrial Unit, Shaftesbury Avenuerooftop solarrooftop solar0.4approved, not builtupdated Oct 2024Sep 2024granted Oct 2024Oct 2024South Tyneside4.3
Whitley Road, Holystonebattery storagebattery storage—application withdrawnupdated Jun 2026Aug 2022—Jun 2026North Tyneside4.3
Soil Machine Dynamic, Davy Bankrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Feb 2024granted Feb 2024Mar 2024North Tyneside4.5
Hebburn Lakes Primary School, Campbell Park Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Nov 2025Jan 2026South Tyneside5.2
Walker Riverside Academy - Photovoltaic Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jun 2021Apr 2021granted Jun 2021Jun 2021Newcastle upon Tyne6.2
Tyneview Primary School, Winslow Placerooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Newcastle upon Tyne6.4
Benfield School, Benfield Roadrooftop solarrooftop solar0.4approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Newcastle upon Tyne6.5
Benfield School, Benfield Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Newcastle upon Tyne6.5
Armadillo Self Storage, Heatonrooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Newcastle upon Tyne6.5
Walkergate Primary School - Photovoltaic Panelsrooftop solarrooftop solar—approved, not builtupdated May 2021Apr 2021granted Jun 2021May 2021Newcastle upon Tyne6.7
Benfield Business Park, Benfield Road -Solar Panelsrooftop solarrooftop solar0.7approved, not builtupdated Aug 2024Jun 2024granted Jul 2024Aug 2024Newcastle upon Tyne6.9
Unit 1, Walker Riverside, Wincomblee Road -Photovoltaic Panelsrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025Newcastle upon Tyne7.1
Seghill Household Waste Recovery Centrebattery storagebattery storage—application submittedupdated Jan 2026Dec 2025—Jan 2026Northumberland7.3
Seghill Household Waste Recovery Centrebattery storagebattery storage—application submittedupdated Feb 2026Dec 2025—Feb 2026Northumberland7.3
Corchester Walk Solar Photovoltaic Panels & Air Sourced Heat Pumpsrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jan 2022Jan 2022granted May 2022Jan 2022Newcastle upon Tyne7.3
Planet Place, Stephenson Industrial Estate - Unit 27 - Battery Energy Storagebattery storagebattery storage—application submittedupdated Jun 2025Apr 2025—Jun 2025North Tyneside7.4
Ravenswood Primary School, Ravenswood Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023Newcastle upon Tyne7.5
Quorum Building, Benton Lanerooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026North Tyneside7.6
Donwood Double Glazing, Stonehills Buildings - Unit A23 - Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025Gateshead7.8
Hadrian Square - Photovoltaic Panelsrooftop solarrooftop solar0.3approved, not builtupdated Oct 2021Aug 2021granted Sep 2021Oct 2021Newcastle upon Tyne8.2
YHN House, Benton Park Road- Solar Photovoltaic Panelsrooftop solarrooftop solar0.3approved, not builtupdated Jan 2022Nov 2021granted Dec 2021Jan 2022Newcastle upon Tyne8.5
David Lloyd Leisure, Castles Farm Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Newcastle upon Tyne8.6
Big Yellow Self Storagerooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jun 2025Jul 2025Gateshead8.8
Robert Duncan Timber Limited, Green Lanerooftop solarrooftop solar0.2approved, not builtupdated Feb 2023Dec 2022granted Jan 2023Feb 2023Gateshead8.9
Newington Road West Depotrooftop solarrooftop solar0.2approved, not builtupdated Feb 2022Dec 2021granted Feb 2022Feb 2022Newcastle upon Tyne9.1
AESC UK, Giga Factories, Plot 2 - Plant 3, Warehouse, Office & Sub-stationsbattery storagebattery storage—approved, not builtupdated May 2026Apr 2024granted Apr 2026May 2026South Tyneside9.1
Ouseburn Trust, Lime Street Solar Panels & ASHPsrooftop solarrooftop solar0.3application submittedMay 2026——Newcastle upon Tyne9.1
Neilson Roadsolar farmsolar farm0.9approved, not built may be out of dateupdated Feb 2022Oct 2021granted Dec 2021Feb 2022Gateshead9.3
Faltec, International Driverooftop solarrooftop solar0.7approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Sunderland9.6
Royal Grammar School, Eskdale Terracerooftop solarrooftop solar0.5approved, not builtupdated Apr 2023Feb 2023granted Mar 2023Apr 2023Newcastle upon Tyne9.6
Newcastle University, Robinson Libraryrooftop solarrooftop solar0.2approved, not builtupdated Feb 2022Feb 2022granted Mar 2022Feb 2022Newcastle upon Tyne9.9
Sterling Pharma Solutionsrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026North Tyneside10.0

Distance from the average position of the NE29 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7430090.5
Rooftop solar411400018.9
Wind turbine210000.8
Battery storage145520180

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Blyth Offshore Wind Test Site41.5operationalupdated Jul 201818.4
Blyth Offshore Wind Farm Phase 2 Demonstrator Project58.4approved, not builtupdated Apr 202218.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How North Tyneside decides solar, wind and battery applications

ApplicationsNorth TynesideUK
Decided applications (solar, wind, battery)1410,236
Refused0 (0%)19%
Solar refused0 of 1112%
Battery storage refused0 of 316%
Median time from submission to decision7.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in North Tyneside

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE29, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.