Standby Embedded Stor Power Plant (20 MW battery storage)

Standby Embedded Stor Power Plant is a 20 MW battery storage project in North Tyneside, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2022; the record was last updated on 16 January 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
under constructionstatus in REPD
16 January 2023record last updated
North Tynesidecouncil area

Planning timeline

DateStage
22 April 2021Application submitted
16 June 2021Planning permission granted
1 October 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
under construction
Record last updated
16 January 2023
Operator or applicant
Green Frog Power 214 Limited
Planning authority
North Tyneside
Planning application reference
21/01109/FUL
Address (REPD)
Standby Embedded Stor Power Plant, High Flatworth, Tyne Tunnel Trading Estate, North Shields
Council area (by location)
North Tyneside
Time to decision
8 weeks
Name in REPD
Standby Embedded Stor Power Plant - Battery storage
REPD reference
9010

Who decides

ApplicationsNorth TynesideUK
Decided applications (solar, wind, battery)1410,236
Refused0 (0%)19%
Solar refused0 of 1112%
Battery storage refused0 of 316%
Median time from submission to decision7.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tynemouth Energy Storage System (TESS)battery storage25operational2.8
Church Bankbattery storage100application submitted2.8
Port of Tynebattery storage35operational3.4
Backworth Lane, Backworth Solar Farmsolar farm28approved, not built6.3
Benton Lane, Quorum Business Parksolar farm8application submitted6.8
West Boldon Substationbattery storage60approved, not built7.3
Seghill Household Waste Recovery Centresolar farm5.8application submitted7.4
Seghill Household Waste Recovery Centre -Solar Panelssolar farm5.8application submitted7.4
E/o the Academy Of Light, Sunderland Road Solar Farmsolar farm40application submitted8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.0036, -1.4822).