West Boldon Substation (60 MW battery storage)

West Boldon Substation is a 60 MW battery storage project in South Tyneside, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 December 2024, not yet built; the record was last updated on 15 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWbattery storage
approved, not builtstatus in REPD
15 July 2025record last updated
South Tynesidecouncil area

Planning timeline

DateStage
17 July 2023Application submitted
21 June 2024Refused by the planning authority
20 September 2024Appeal lodged
10 December 2024Planning permission granted
10 December 2024Appeal allowed
10 December 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
60 MW
Status (REPD)
approved, not built
Record last updated
15 July 2025
Operator or applicant
Whirlwind Energy Storage Limited
Planning authority
South Tyneside
Planning application reference
ST/0486/23/FUL
Appeal reference
APP/A4520/W/24/3350689
Address (REPD)
East of the West Boldon Substation, 400 metres south of the A184 and 300m East of the A189 in South Tyneside
Council area (by location)
South Tyneside
Time to decision
73 weeks
Name in REPD
West Boldon Substation - Battery Energy Storage
REPD reference
14408

Who decides

ApplicationsSouth TynesideUK
Decided applications (solar, wind, battery)1210,236
Refused1 (8%)19%
Solar refused0 of 912%
Onshore wind refused0 of 145%
Battery storage refused1 of 216%
Median time from submission to decision6.1 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Washington Road Solar Farmsolar farm20approved, not built2.0
Woodhouse Farmsolar farm11refused3.8
Port of Tynebattery storage35operational4.3
Church Bankbattery storage100application submitted4.4
E/o the Academy Of Light, Sunderland Road Solar Farmsolar farm40application submitted4.7
Usworth House Farm, Peareth Hall Road Solar Farmsolar farm27.3refused5.5
Fox Cover Roadbattery storage30approved, not built5.9
Hastings Hill Farm, Foxcover Roadbattery storage38approved, not built6.2
Standby Embedded Stor Power Plantbattery storage20under construction7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9389, -1.4674).