Woodhouse Farm (11 MW solar farm)

Woodhouse Farm is an 11 MW solar farm project in Sunderland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 15 January 2015; the record was last updated on 21 January 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
refusedstatus in REPD
21 January 2015record last updated
Sunderlandcouncil area

Planning timeline

DateStage
10 October 2014Application submitted
15 January 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
refused
Record last updated
21 January 2015
Operator or applicant
European Energy Photovoltaics
Planning authority
Sunderland
Planning application reference
14/02132/FUL
Site area
19.7 ha
Address (REPD)
Wood House Farm, Ferryboat Lane, North Hylton, Sunderland
Council area (by location)
Sunderland
Time to decision
14 weeks
REPD reference
1839

Who decides

ApplicationsSunderlandUK
Decided applications (solar, wind, battery)4010,236
Refused3 (8%)19%
Solar refused3 of 3112%
Onshore wind refused0 of 445%
Battery storage refused0 of 516%
Median time from submission to decision8.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Washington Road Solar Farmsolar farm20approved, not built1.7
Fox Cover Roadbattery storage30approved, not built2.1
Hastings Hill Farm, Foxcover Roadbattery storage38approved, not built2.5
West Boldon Substationbattery storage60approved, not built3.8
Usworth House Farm, Peareth Hall Road Solar Farmsolar farm27.3refused6.0
E/o the Academy Of Light, Sunderland Road Solar Farmsolar farm40application submitted6.0
Mary Avenue, Birtleybattery storage71refused7.9
Port of Tynebattery storage35operational8.0
South Sharpley Wind Farm (Revised)wind farm7.5operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.9053, -1.4617).