Energy Projects Near You

South Sharpley Wind Farm (Revised) (7.5 MW)

South Sharpley Wind Farm (Revised) is a 7.5 MW wind farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 January 2013; the record was last updated on 24 January 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
24 January 2013record last updated
County Durhamcouncil area

Planning timeline

DateStage
1 May 2008Application submitted
24 December 2009Refused by the planning authority
10 April 2011Planning permission granted
10 April 2011Appeal allowed
18 June 2012Construction started
23 January 2013Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
24 January 2013
Operator or applicant
REG Windpower (previously Cornwall Light & Power)
Planning authority
County Durham
Planning application reference
PLAN/2008/0355
Turbines
3
Address (REPD)
South Sharpley Farm, near Seaham, County Durham
Council area (by location)
County Durham
Time to decision
153 weeks
REPD reference
3985

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Eppleton Farm Repoweringwind farm8.2operational2.2
Solar Farm at E/O Stockton Roadsolar farm48application submitted2.9
Hawthorn Pit -Solar Farmsolar farm49.9approved, not built3.4
Hawthorn Wind Farmwind farm7.5application withdrawn4.1
Woodlands, Windermere Roadbattery storage90application submitted4.4
Hawthorn Grid Sitebattery storage49operational4.4
Fox Cover Solar Farm - Ground Mounted Photovoltaic Panelssolar farm8approved, not built4.7
Carrs Farm, South Hettonbattery storage200application submitted4.9
Hallfield Farm, Easingtonbattery storage57application submitted5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8404, -1.4022).