Energy Projects Near You

Hawthorn Pit -Solar Farm (49.9 MW)

Hawthorn Pit -Solar Farm is a 49.9 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 May 2023, not yet built; the record was last updated on 10 July 2024. REPD records the planning permission as expiring on 25 May 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
10 July 2024record last updated
County Durhamcouncil area

REPD records the planning permission as expiring on 25 May 2026, but the project holds a Contracts for Difference award (AR6), so construction may have started.

Planning timeline

DateStage
4 October 2021Application submitted
19 July 2022Refused by the planning authority
12 October 2022Appeal lodged
25 May 2023Planning permission granted
25 May 2023Appeal allowed
25 May 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
10 July 2024
Operator or applicant
Aura Power Developments Limited
Planning authority
County Durham
Planning application reference
DM/21/03420/FPA
Appeal reference
22/00052/REF
Site area
52.0 ha
Address (REPD)
Croup Hill South Of Beaconsyde Farm Broadoaks Murton
Council area (by location)
County Durham
Time to decision
85 weeks
Contracts for Difference
AR6
REPD reference
9799

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hawthorn Grid Sitebattery storage49operational1.2
Woodlands, Windermere Roadbattery storage90application submitted1.2
Carrs Farm, South Hettonbattery storage200application submitted1.7
Hawthorn Wind Farmwind farm7.5application withdrawn2.2
Great Eppleton Farm Repoweringwind farm8.2operational2.4
Hallfield Farm, Easington Solar Farmsolar farm49.9application submitted2.9
Hallfield Farm, Easingtonbattery storage57application submitted2.9
South Sharpley Wind Farm (Revised)wind farm7.5operational3.4
Fox Cover Solar Farm - Ground Mounted Photovoltaic Panelssolar farm8approved, not built4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.81, -1.4049).