Energy Projects Near You

Hawthorn Grid Site (49 MW battery storage)

Hawthorn Grid Site is a 49 MW battery storage project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 September 2024; the record was last updated on 13 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWbattery storage
operationalstatus in REPD
13 February 2026record last updated
County Durhamcouncil area

Planning timeline

DateStage
18 March 2022Application submitted
2 December 2022Planning permission granted
11 September 2024Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49 MW
Status (REPD)
operational
Record last updated
13 February 2026
Operator or applicant
Harmony Energy Limited
Planning authority
County Durham
Planning application reference
DM/22/00747/FPA
Address (REPD)
Hawthorn Grid Site Murton
Council area (by location)
County Durham
Time to decision
37 weeks
Name in REPD
Hawthorn Grid Site - Battery Storage
REPD reference
10896

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Woodlands, Windermere Roadbattery storage90application submitted<0.1
Carrs Farm, South Hettonbattery storage200application submitted0.6
Hawthorn Pit -Solar Farmsolar farm49.9approved, not built1.2
Hawthorn Wind Farmwind farm7.5application withdrawn1.7
Hallfield Farm, Easingtonbattery storage57application submitted1.8
Hallfield Farm, Easington Solar Farmsolar farm49.9application submitted1.8
Peterlee Solar Farmsolar farm5operational3.4
Great Eppleton Farm Repoweringwind farm8.2operational3.6
Hackworth Road, North West Industrial Estatesolar farm15.4application submitted3.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.8014, -1.3942).