Peterlee Solar Farm (5 MW)

Peterlee Solar Farm is a 5 MW solar farm project in County Durham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2016; the record was last updated on 16 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
16 June 2016record last updated
County Durhamcouncil area

Planning timeline

DateStage
23 July 2015Application submitted
14 January 2016Planning permission granted
15 January 2016Construction started
30 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
16 June 2016
Operator or applicant
Zaravolt Development
Planning authority
County Durham
Planning application reference
DM/15/02290/FPA
Site area
10.1 ha
Address (REPD)
Land North Of Mill Hill, North West Industrial Estate, Peterlee
Council area (by location)
County Durham
Time to decision
25 weeks
REPD reference
5694

Who decides

ApplicationsCounty DurhamUK
Decided applications (solar, wind, battery)8910,236
Refused22 (25%)19%
Solar refused7 of 5112%
Onshore wind refused13 of 3045%
Battery storage refused2 of 816%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed5 / 5—

UK: all UK planning authorities. Counted under these REPD planning authority names: County Durham, Durham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hackworth Road, North West Industrial Estatesolar farm15.4application submitted0.3
Hallfield Farm, Easington Solar Farmsolar farm49.9application submitted2.0
Hallfield Farm, Easingtonbattery storage57application submitted2.0
Carrs Farm, South Hettonbattery storage200application submitted2.9
Haswell Moorwind farm10operational3.0
Edder Acres Farmwind farm5refused on appeal3.1
Woodlands, Windermere Roadbattery storage90application submitted3.4
Hawthorn Grid Sitebattery storage49operational3.4
Hawthorn Pit Green Energy Parkbattery storage1,000application submitted3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7752, -1.3655).